WA could be solar exporter, but it needs a solar industry first

Western Australia’s Pilbara region must first prove its ability to deliver cost-effective utility-scale solar and storage, before it can become a regional hub for solar energy exports to Asia, a new report has found.

The Pilbara Solar Export Pre-Feasibilty Study, which was officially released by the Pilbara Development Commission on Tuesday morning, examines a ‘pilot’ project, to provide 3GW of Pilbara-generated solar to the Java grid.

Screen Shot 2017-08-29 at 2.19.47 PM copy

As we reported here yesterday, the report found that a commercial case for the project could be established within five to 10 years, including the construction of a $9.5 billion, 1500km sub-0sea cable from the Dampier Peninsula to east Java and three 1GW solar farms.

“The preliminary engineering and costing analysis shows that the 3GW solar generation Pilot Project with HVDC connection to Java may have commercial potential,” it says, adding that “the falling costs of solar and storage may confirm this in the near future.”

PDCchart1PDCTable3

The figures the report comes up with on cost are 18-25 c/kWh “over the long term,” with earnings of 19-20 c/kWh from the solar feed-in tariff applicable in Java.

But, as the report’s authors – Samantha Mella, Geoff James and Kylie Chalmers – point out, these figures are subject to numerous uncertainties and even a few unknowns.

“There are technology and supply chain uncertainties on the cost side, and the need for a negotiated outcome recognising strategic benefits on the revenue side,” the report says.

But perhaps most importantly, the report finds that the successful export of solar PV generation from WA’s north-west would depend on first building up a local large-scale solar industry in the Pilbara, where virtually nothing of the sort currently exists.

“The Pilbara must first have a local solar industry to be able to offer Indonesia competitive rates on large-scale solar generation,” the report says.

“Ultimately, cost is the critical factor. The LCOE must be cost-competitive, with the large overhead of the subsea interconnector.

“An experienced solar industry in the Pilbara with a proven ability to deliver cost-effective utility scale solar, potentially with storage, would significantly improve the economic case.

“A local industry will build the solar supply chains and become more competitive with experience and scale,” the report says.

The report recommends the region’s solar generation capacity should be built up by small stages – starting with a 20MW facility and then expanding production to several solar generators each serving a load within the Pilbara (new capacity of 180 MW) – to nurture a local supply industry that can develop projects properly adapted to local conditions.

The report is particularly enthusiastic about the potential for the resource-rich WA region to lead the country – if not the world – in solar-diesel hybrid energy system development, given its proliferation of mining projects currently powered by diesel and gas.

“The Pilbara has over 1,400MW installed capacity of gas and diesel off grid,” it notes. “A successful model for the solar diesel hybrid has been demonstrated in WA with the DeGrussa Mine, owned by Sandfire resources.

“The opportunity to scale up with solar diesel hybrids has the potential to bring many benefits to all stakeholders, regardless of whether an agreement is reached with Indonesia.”

As for the role of WA as a solar exporter to the east coast of Australia, the report says this is “unlikely to be commercially viable as a stand-alone proposition,” due to the market returns being so much lower in the NEM.

Annual revenues from the 3.4GW of solar PV generation are estimated at $1,622 million based on the solar feed-in tariff allocated to Java, the report finds, while they come to just $284 million based on NEM NSW wholesale prices in 2010.

This is a shame, the report notes, considering exporting solar energy from Australia’s west to its east could be a value-adding exercise, all round.

“Due to the time difference, afternoon solar energy in the Pilbara would supply into the evening peak demand on the east coast, and would correspondingly have a high value in the National Electricity Market (NEM). Delivering to the NEM, in addition to Indonesia, would also mitigate the risk of depending on a single market.”

On battery storage, the report notes that the above calculations do not show how the HVDC transmission line could be used more efficiently through the integration of energy storage.

“Battery energy storage can be integrated without increasing LCOE due to improving the HVDC capacity factor and makes the solar generation fully dispatchable, increasing its value to the local and international markets,” the report finds.

As for who might build these gigawatt-scale solar farms, Western Australia’s minister for regional development, Alannah MacTiernan, says the project would be privately funded, with no direct investment from the state.

“We will get feedback from industry players to see what the interest might be and then to see what additional work there needs to be if there is genuine interest in this,” MacTiernan said in a statement on Monday.

The report notes that, in consideration of Native Title laws, and in keeping with corporate social responsibility, there was an opportunity for some Aboriginal groups in the Pilbara to own, or co-own solar farms as income-producing assets.

Comments

5 responses to “WA could be solar exporter, but it needs a solar industry first”

  1. Ken Avatar
    Ken

    Huh?
    A local solar industry in what form?
    Solar projects are made up of components that are pretty much 100% imported from overseas anyway.
    Its cheaper to manufacture those items overseas, and the cost in Australia is lower as a result unless we start adding punitive import taxes.
    All projects in those regional areas and completed on that basis using items imported from elsewhere ( usually overseas) and labour in Australia is mobile and will move to where there are jobs,, but not permanently ( ie.. FIFO).

    Its aptly named as a “Pre” feasibility study.
    Just an idea at this stage and years off becoming a plan before it can become a reality.

    1. Geoff James Avatar
      Geoff James

      One thought Ken is that conditions in the Pilbara are harsh, and if solar plants are really going to survive around 25 years, the usual assumption, then some specially tailored engineering will be needed to deal with rocky soils, cyclones, and extreme temperatures. There’s opportunity for a local industry to develop solar engineering that is cost-effective and highly scalable. Including storage integration in one or more forms.

      As for continuity of employment, If the idea takes off it won’t be a single solar build, but a continuous rollout of solar development driven by the ASEAN market. It’s potentially a multi-decadal program which should support a local supply chain. And at some point the maintenance of existing plant will be a bigger employer than the building of new.

      1. Chris Jones Avatar
        Chris Jones

        The other problem is with seabed earthquakes causing cable breaks. Considering the communications cables from WA to Indonesia have broken a number of times in the last 10 years, this is a real risk. Repairs can take quite some time as well, as there are not that many ships capable of repairing the lines.

  2. Ian Avatar
    Ian

    $9.5 billion for the 3 GW cable that is 1500km long. Presumably the major cost is the actual cable and the connections at each end are ‘trivial’ in cost. The cost per km would be $6.3 million/km. The current Basslink is 270km long . So, for a back of envelope pre-feasibility study for a 3GW basslink: $1.7 billion.

    What about it then . Let’s practice these HVDC’s with a new 3GW Basslink. We can use the ‘learnings’ to consider this much longer subsea link to Indonesia.

  3. Malcolm Green Avatar
    Malcolm Green

    This is a great idea.
    We could have a world wide web of electricity power line inter-connections.
    Buckminster Fuller proposed this as an idea in the 1960’s ‘World Game’ as the highest priority objective to make the world work for everyone !

Get up to 3 quotes from pre-vetted solar (and battery) installers.