First Solar reaches financial close for Beryl solar farm in NSW

Artist impression of Beryl solar farm
Artist impression of Beryl solar farm
Artist impression of Beryl solar farm

The 87MW Beryl solar farm in New South Wales is set to be the next major renewable project to roll off the line after developer First Solar reached financial close last week.

Beryl, located five kilometres from the town of Gulgong in the state’s central west, is one of the biggest solar projects in the state to reach financial close since the completion of the 102MW Nyngan solar project, although there are several bigger projects on the horizon.

First Solar is also about to complete the 41.5MW Manildra project, which is undergoing commissioning now. Neoen has signed a PPA agreement for the 150MW Coleambally solar project, while Maoneng has a PPA for the 250MW Sunraysia project near Balranald.

The contract for the $150 million project has been awarded to Downer Group,

Steven Jackson, First Solar’s vice president of Asia Pacific, said the Beryl project will be one of the first to use the company’s new Series 6 thin film photovoltaic (PV) modules.

(“(This means), the Beryl Solar Farm will maximise the energy produced from the site and deliver a lower levelised cost of electricity,” he said in a statement.

“With a nameplate capacity of up to 445W and 18% efficiency, First Solar Series 6 modules are the highest power PV module available for large-scale solar projects.

The project will also use single axis tracking technology and Ingeteam inverters.

Transmission company Transgrid also announced that the financial close meant it could commence additional planning work as part of the connection process.

“The project is located approximately 250 metres south of TransGrid’s Beryl Substation, so we havebeen able to offer a very competitive and attractive asset connection plan to First Solar,” TransGrid’s head of business growth Richard Lowe said in a statement.

“The Beryl Solar Farm will connect directly into TransGrid’s high-voltage electricity transmission network via a 66kV connection to a new bay at Beryl Substation.

“This connection will allow the export of 87 megawatts of power into the National Electricity Market – enough to serve the needs of approximately 25,000 average NSW homes, while the associated carbon emission displacement is equivalent to taking about 45,000 cars off the road.”

TransGrid will build and operate a new substation at the solar farm site to connect to TransGrid’s existing Beryl substation. Construction of connection assets to follow in the second half of 2018.

Comments

6 responses to “First Solar reaches financial close for Beryl solar farm in NSW”

  1. George Darroch Avatar
    George Darroch

    It’s a good location, with high insolation and an apparently uncongested grid connection. Looking forward to seeing this reach completion in the next year.

  2. David leitch Avatar
    David leitch

    No ppa?

    1. Giles Avatar

      We understand there is, but not announced yet. If you like anagrams then i’m sure you will SWooN with excitement when the news is formalised.

  3. Paul Hartmann Avatar
    Paul Hartmann

    Why is it fine to encourage large solar farms and at the same time restrict roof top to such small scale? I also thought we were close to over supply until storage becomes more abundant? At least this is the reason given for roof top restrictions.

    1. Peter Campbell Avatar
      Peter Campbell

      A restriction on roof top solar might be due to limits on the local transformer at the end of the street or at the next level up in the network. Still a long way to go before the coal power stations have to cut right back during the day.

  4. shiner2348 Avatar
    shiner2348

    Enjoying your discussions but please stop using ACRONYMS all the time we have to google what they mean and it’s a pain in the arse eample.Power Purchase Agreements,(PPAs) Thank you

Get up to 3 quotes from pre-vetted solar (and battery) installers.