State approves six new wind and battery projects before going into election caretaker mode

A composite of Victorian Premier Ben Carroll and Opposition Leader Jess Wilson as the major parties outline competing hospital funding and healthcare policies ahead of the Victorian state election, created on Friday, October 30, 2026. (AAP Graphics/Joanna Kordina, AAP Image/Con Chronis, Joel Carrett, Jay Kogler) NO ARCHIVING

Victoria’s planning minister Sonya Kilkenny has approved two wind projects and four utility batteries in a last-minute blitz of activity ahead of going into caretaker mode on Tuesday night. 

The total development value of the six projects is nearly $4 billion, according to planning documents. 

The move comes as the state races to lock in new energy generation before the 2028 closure of the 1.48 gigawatt (GW) Yallourn coal-fired power station and as the Labor government tries to embed its renewable legacy before what is shaping up as a tough day at the polls. 

The two wind projects that now have state approval to proceed (but still need federal green tick) are Squadron Energy’s $1.5 billion 420 MW Moreton Hill project and Virya Energy’s $2 billion Meering West project, a 1.3 GW wind project with a 500 MW, 1000 megawatt-hour (MWh) battery.

The approvals came in on Friday and Monday, just before the hard stop of 6pm on Tuesday evening when the government shifted into caretaker mode ahead of the election on November 28. 

Also approved were European Energy’s 600 MW/1,200 or 2,400 MWh Gippsland battery, Potentia Energy’s 200 MW/800 MWh Tragowell battery, and the smaller Cobden and Camperdown batteries, both of which are being proposed by Australian Renewable Energy Services.

The last minute approvals mean the projects should not be affected by the Coalition’s promise of 2 km buffer zones in the case of the wind projects – nor its plan to pivot the state’s future electricity system from renewable generation to gas, if it wins power later this month.

However, they might still feel the effects of the Coalition proposal to pause and review transmission plans across the state, and cancel the interconnector with New South Wales (NSW), the VNI West project, on the grounds of its ballooning cost.

While the transmission project has its state planning approval in hand, premier Ben Carroll has promised his own economic review of WRL if Labor wins, to curry favour with disgruntled voters. 

Environment Victoria chief Jono La Nauze says pausing and cancelling transmission builds will be “act of economic self harm”.

“Building those transmission lines still comes out at a positive cost-benefit to consumers. That’s why they’re being built,” La Nauze tells Renew Economy.

“Of course it costs something to build something, but it doesn’t mean you’re going to lose out. The benefit that it brings in terms of new and the lowest cost generation far outweighs the cost of building it.

“It’s like adding up the cost of building the freeway but none of the benefits of using it.”

Environmental Victoria’s modelling shows that a five year delay in building transmission and bringing new renewables online will add $33 billion in costs to the Victoria economy, or $500 a year to household power bills.

La Nauze says cancelling some transmission projects entirely and replacing the possible and probably future renewable generation they would enable with gas power is “economic insanity”.

“Right now wind and solar in Victoria cost half as much per megawatt hour as coal and gas, and that differential is only going to keep growing as Victoria’s gas supplies run out,” he says.

“Without more transmission you can’t have more wind and solar.”

At risk?

Of the newly permitted projects, the one most threatened by Coalition plans are the 155 turbines at Meering West.

It is supposed to connect directly into VNI West, which will carve a line through the project site. 

Virya Energy general manager Steve Crowe has previously told Renew Economy that the landowner-led project in the north of the state will revert to an original plan to build a power link to Kerang, if VNI West is cancelled. 

The Squadron project, which is 35km southwest of Ballarat in central-west Victoria, is positioned along the line where the Western Renewables Link (WRL) is supposed to go. 

The latest approvals don’t mean the projects have a completely clear run out of development and into construction, yet. 

Both wind projects still need federal EPBC approval. 

Squadron’s Moreton Hill wind project will have up to 62 turbines, producing enough electricity to power around 260,000 homes, and connect into the electricity network via a new underground 220kV powerline to the Berrybank terminal station to the south. 

None of the batteries have been referred for federal environmental assessment. 

While Moreton Hill only received six objections from eight submissions, the Meering West project was a lightning rod for opposition, attracting 102 objections of 108 submissions — including from the Gannawarra shire council which until recently was led by new One Nation candidate Garner Smith.

Energy pivot

Over the last 12 years Labor has built planning, policy and regulatory infrastructure to support a renewable-first electricity system in Victoria. 

The Coalition wants to shift away from renewables to focus on gas.

It is promising to fill the gap left by Yallourn in mid-2028 with gas under a new Energy Security Requirement, and encourage greater gas use by households by removing a ban on gas connections for new build homes. 

It is also planning to drop renewables from the state’s streamlined planning system and allow post-approval merit appeals again. 

Last week, Liberal shadow energy minister David Davis toned down the rhetoric somewhat for a renewable energy-heavy audience at the All Energy conference, promising the transmission review would be “short, sharp and independent”.

He did not put a timeline on how short, but conceded that renewables will still make up the largest chunk of generation in the state.  

Davis criticised the amount of generation that has been built in Victoria in Labor’s 12 years in office and underscored his view that more gas is needed to fill the gap. 

But neither Davis nor the Coalition are yet to outline how gas, which continues to drive electricity prices higher, will lower bills for Victorians.

To support independent media, and help combat the spread of deliberate misinformation and disinformation about the energy transition, you can click here to make a one off donation or become a regular supporter of Renew Economy.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

9 Comments