Home » Solar » Neoen pockets significant damages for delays to Australia’s biggest solar project

Neoen pockets significant damages for delays to Australia’s biggest solar project

western downs solar farm neoen
Western Downs solar farm. Image supplied.

French renewable energy developer says it has received significant “liquidated damages” in the latest half year arising from delays in the delivery of the country’s biggest solar project.

The 400MW (ac) Western Downs solar farm in Queensland is the biggest in Australia, although it may be shortly overtaken by the New England solar farm in northern NSW that is being built by Acen.

The Western Downs farm reached full commissioning only recently, and like many wind and solar projects in Australia suffered delays for a bunch of different reasons, and often relate to delays in equipment or connection and commissioning problems.

Neoen has previously said delays in module deliveries would likely mean that the Western Downs solar farm was not complete by late last year, as originally scheduled, but it made clear it was protected by liquidated damagess clauses.

Neoen says it likes to lock in clauses for liquidated damages in its EPC contracts, even though they tend to be more expensive, because it protects against losses. It has exercised similar damages claims at its smaller solar farms in western NSW, and at the Bulgana green energy hub in Victoria.

“Our preference is for turnkey contracts  …. meaning that in case of contractors are late, in case the performance is not there, we are well compensated for that,” CEO Xavier Barbaro said in a conference call.

“They are not as competitive …. but the evidence we think is that in the case plant is delayed, we can get those precious liquidated damages.” The scope of damages is rarely revealed.

The Western Down EPC contractor is India-based Sterling and Wilson Renewables, which has cited several liquidated damages claims in its result result presentations, but has not identified which projects.

It is largely protected from such payouts by a funding agreement from its new major shareholder, the Indian energy giant Reliance, unlike other EPC contractors that have fallen by the wayside under the weight of damages claims.

Neoen did not quantify the extent of the damages claims for the delays at Western Downs, but they appear to have been significant.

It was one of the main reasons – along with the start of production at the facility – for a 29 per cent lift in adjusted EBITDA from its solar division to €114.8 million in the first half, and lifted its profit margins to 99.9 per cent.

Liquidated damages were also paid for the delayed commissioning of power plants in France and Ireland.

The output of the Western Downs solar farm is contracted mostly to the state-owned CleanCo, and is part of a green energy hub which will also feature a big battery project.

Neoen said earlier this week that the battery component would be expanded from the original plan of 200MW and two hours storage (400MWh), to a new size of 270MW and 540MWh).

That will make it easily the biggest battery in Queensland, and the largest battery in Australia to be directly located next to a solar facility. That battery component is being built by UGL, using Tesla Megapack technology.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Related Topics

Latest posts

S-curve modelling says renewables can kick coal out of Australia by 2032. But is this soon enough?

S-curve modelling says renewables can kick coal out of Australia by 2032. But is this soon enough?

In the race to renewables, the big question is whether “faster than we thought” is the same as “fast enough.” S-curves say we can do the first. Nothing in the modelling tells us we’re on track for the second.
“It’s a commercial system. And it has a customer:” Sodium-ion battery sale hailed as a first for Australia

“It’s a commercial system. And it has a customer:” Sodium-ion battery sale hailed as a first for Australia

The sale of a 100 kilowatt and 200 kilowatt-hour sodium-ion battery system is being claimed as an Australian first – and may herald next generation of storage tech.
Energy Insiders Podcast: Will the green bank save the Tomago deal?

Energy Insiders Podcast: Will the green bank save the Tomago deal?

CEFC boss Ian Learmonth explains why big wind projects may finally get delivered this year. Plus: Tomago aims for 100 pct renewables, and the big utility profits.
Balcony solar or building integrated PV? The emerging options for apartment dwellers and owners

Balcony solar or building integrated PV? The emerging options for apartment dwellers and owners

A Victorian parliamentary inquiry on apartment energy issues has recently reported and identified several issues that require urgent attention to address the failures of energy policy. One interesting issue that relates to both high rise apartments, and plug-in ‘balcony solar’, is where solar fits into apartment occupant energy costs.  High rise apartment buildings have very […]