Home » Commentary » Why the Renewable Energy Target won’t be met in 2018

Why the Renewable Energy Target won’t be met in 2018

Shuttershock
Shuttershock

Based on analysis within our latest Renewables Report, Green Energy Markets has concluded that supply will fall short of the Large-scale Renewable Energy Target (RET) by 2018.

This will mean power retailers, and consequently their customers, will be paying the shortfall penalty (this is $65 for every megawatt-hour of renewable energy short of the target, which effectively works out to $92.86 because the penalty isn’t a tax deductible expense).

So how did it come to this? And what, if anything, should we do about it?

The first thing to note is that any shortfall is not for lack of renewable energy projects. Nor is the problem to do with the fundamental economics of those projects.

Rather, the shortfall is a product of wounded confidence in the finance community. That is quite understandable given that Dick Warburton, while chair of the Abbott Government review of the RET, told the Australian Financial Review the entire scheme could be scrapped (akin to cutting projects’ revenue in half) without a cent of compensation. On another occasion, Tony Abbott revealed to Alan Jones that he’d have liked to have scrapped the RET altogether.

A majority within the government baulked at such extreme measures, but it left financiers rattled. Such a battering to confidence can only be healed by positive experience and therefore the passage of time. Unfortunately, time is in short supply.

Back in late 2013, when financiers put a hold on renewable energy investment to await clarity about the Abbott Government’s policy, we knew there was a shortfall of renewable energy certificates awaiting in 2018.

Given the two year lag typically involved in financing and constructing renewable energy projects, things could have been OK if we’d resolved the uncertainty reasonably quickly, even if the target remained at 41 terrawatt-hours (TWh).

But by the time it was ultimately resolved in mid-2015 there was precious little time left, and financiers were fearfully cowering in their bunkers.

In April last year, Green Energy Markets estimated that an LRET target very similar to the 33TWh target that was ultimately enacted could be achieved provided the market committed investment to construct 1,200MW in 2015, which would need to be followed by another 2,500MW in 2016.

Unfortunately,  the country committed to less than 500MW and most of that won’t even contribute towards the 33TWh target, instead being used by the ACT Government to count towards their own 90% renewable energy target.

In light of this, our December Renewables Report estimates 4,400MW would need to be committed in 2016 to avoid a shortfall in 2018. We’ve underestimated the ability of the renewables industry to deliver in the past but this turnaround appears inconceivable.

The price for Large-scale Renewable Energy Certificates known as LGCs suggests this is the consensus view of other participants.

Spot prices for LGCs have soared past the nominal shortfall penalty of $65 and are now in the low $80’s. Meanwhile some forward trades beyond 2017 have traded only a few dollars off the tax-effective level of the shortfall penalty of $92.86.

Screen Shot 2016-02-11 at 12.31.43 PM
LGC spot price history

Such a price for LGCs is completely out of alignment with the underlying economics of large scale renewable energy projects. The ACT Government’s wind energy procurement auction managed to secure 3 projects at a cost of $81.50, $87 and $92 per MWh.

Taking the highest price of $92/MWh as a guide and given these projects would receive somewhere between $35 and $60 per MWh from selling the underlying electricity, this roughly implies a top up from LGCs of about $32 to $57 per certificate to make such projects viable. That’s an awful lot less than current spot prices.

The discrepancy between the market and economic fundamentals comes down to financiers’ lack of confidence about the long-term settings for the LRET. They’re prepared to build projects for the ACT Government for $81.50 to $92 per MWh because they don’t need to worry about what a future Federal Government might do with the LRET.

Confidence should recover over time provided the Federal Government resists the temptation to intervene in the market and the Environment Minister’s supportive statements about the scheme spread to other Cabinet Ministers.

However, over 2016 project commitments are likely to be mainly driven by state governments and government-owned retailers who are offering contracts that provide some long-term price certainty for project developers.

Our detailed assessment of these state government procurement initiatives, alongside ARENA’s large-scale solar auction, indicate 1100MWs could be committed this year.  Coupled with some large behind the meter rooftop solar installations, it’s realistic to expect a break-out year for large-scale solar of more than 450MW in project commitments.

The figure of 1,100MW falls well short of what’s required to ensure the RET target is met in 2018 and also makes achievement of targets in subsequent years very challenging. But it is still a significant source of demand that will finally allow the renewables industry to regain their feet and rebuild their confidence.

It is no doubt deeply disappointing for everyone that Australia will fall short of the target, incurring unnecessarily high LGC prices and penalties when it could have been easily avoided. However if politicians start talking about tinkering  with the scheme yet again, they’ll make things worse.

The current high LGC prices are acting to lure investors and power retailers out of their bunkers in spite of their wounds. Alinta’s tender for renewable energy and AGL’s 1000MW Powering Australian Renewables Fund announcement are promising signs.

Investment grade large power consumers are also wising up to the fact they’re paying too much for LGCs and could instead contract directly to support new projects. With time this will ultimately drive enough supply to overcome the shortfall and bring LGC prices down to levels in line with economic fundamentals.

Tristan Edis is Director – Analysis and Advisory for Green Energy Markets’ . He was previously Editor of Climate Spectator.

Comments

11 responses to “Why the Renewable Energy Target won’t be met in 2018”

  1. Vernham Avatar
    Vernham

    None of what is said here answers the question of the unreliability of supply when it is needed. There is nothing in this story which could possibly give anyone a nice feeling that prices will not continue to constantly fluctuate. Also the ACT has signed contracts yes, but can these contracts ensure they receive renewable energy, especially when the turbines are not turning at full capacity 24/7.

    1. Tomfoolery Avatar
      Tomfoolery

      What on earth are you on about?

      1. John Saint-Smith Avatar
        John Saint-Smith

        A troll – ignore.

  2. Tim Buckley Avatar
    Tim Buckley

    Tristan, excellent to see you back online. Great article. Our Federal government needs to give financial markets confidence that transparency, longevity and certainty is finally here in Australian electricity market planning. Electricity assets are long dated and investors need clarity to drive the sector transformation. To-date the evidence from the Turnbull government is weak, a brake on new investments.

  3. Ron Horgan Avatar
    Ron Horgan

    Why can’t the states follow the ACT lead? We don’t have leadership from Canberra but the ACT is becoming the de-facto leader of the nation when it comes to progress.

  4. Andrew Avatar
    Andrew

    Good points and comments.
    A successful LRET scheme needs good governance and a steady hand; unfortunately our government has undermined all credibility in that respect with conflicting rhetoric and behaviour that disrespects investors and industry. The LRET is poorly designed anyway; with no minimum floor price or end date LGCs are not bankable revenue.
    The ACT have done exactly the right thing. Industry responds well to delivering bounded solutions. By hedging volatile energy and LGC prices with a fixed price fixed term PPA, industry can competitively bid on cost and performance to deliver greenfield renewable generation at the best price. My compliments to those responsible for the ACT scheme.
    Of course, ACT takes the risk on the difference between energy price and LGCs compared to its PPA price. But currently, for each $81.50/MWh paid to its cheapest wind farm, it reaps $50/MWh (say, electricity price) plus $80/MWh LGC, a total of $130/MWh, or a net benefit of $48.50/MWh that the rest of Australia is compensating ACT! Being first mover looks like a good risk!

  5. David Osmond Avatar
    David Osmond

    In the 2nd round of the ACT Government wind auction, they achieved a cheapest price of $77/MWh, even cheaper than the $81.50 price achieved in round 1.
    http://www.canberratimes.com.au/act-news/neoen-hornsdale-wind-farm-signs-up-for-record-low-renewables-tariff-20151219-glrqxx.html

  6. Tim Forcey Avatar
    Tim Forcey

    Yaaay. Tristan’s back…

    1. John P Avatar
      John P

      Yes, welcome back Tristan. I feel better already.

  7. Sue Morrison Avatar
    Sue Morrison

    I’ve just been made aware the Coalition Government is 3 years behind in surrendering ICUs equivalent to GreenPower sales under the National GreenPower Program, thereby undermining their “additionality” (which is the whole purpose of the GreenPower Program!).

    https://www.climatechest.org.au/c3_greenpower_additionality_v3.pdf

    Can anyone here shed light on this? Another example of how the LRET is being undermined by the current government or is it just plain incompetence? Either way, questions need to be asked…

  8. JeffJL Avatar
    JeffJL

    What hack have you brought in now Miles. A Tristian Edis? Surely there is somebody better out there to write on this site.

    Why not get somebody who has spent some time in a big organization writing about this stuff before. There has to be one or two who have been dis-guarded in the Murdoch’s drive for controversy.

    Could you not find somebody who perhaps worked for you before and you mentored.

    WELCOME BACK TRISTIAN! I’VE MISSED YOU.

Get up to 3 quotes from pre-vetted solar (and battery) installers.