Gas

Snowy warns of “odour and plume” as it commissions diesel generators at delayed and over-budget peaking plant

Published by

Snowy Hydro has warned local residents of “odour and plume” as it commissions the diesel component of its delayed, over-budget and controversial Kurri Kurri power station, but promises the impacts will be less severe than last time.

Snowy Hydro caused outrage in the local community because of the intensity of the plume and odour during initial testing of the diesel turbines last year, which it admits in a media statement on Monday was “greater than we anticipated.”

It says that testing for the commissioning process, due start on Friday, will take place at night, over the course of about four weeks.

“While there will still be some odour and plume, we do not expect this over an extended period,” the company said. “We have learned from last year’s events and community impacts, and have worked with the manufacturer to ensure we are doing everything possible to minimise impacts.”

The 660 megawatt (MW) Kurri Kurri power station is already running two years late, and its blown its original budget by a factor of more than two, with the original $610 million estimate leaping to $1.3 billion, sparking a dispute with its major contractor UGL.

The need for the project has always been questioned, and Snowy Hydro CEO Dennis Barnes even conceded last month that it was not needed by the market at the moment – which is not surprising given the rising dominance of battery storage to meet evening and other demand peaks.

“As always, when you get to the end of these projects, you’ve got to sort out the commercials, and at the moment, the market doesn’t need it,” Barnes told the AFR last month.

“There’s plenty of renewables, the climate has been benign, so it’s fully commissioned on gas, but to close it out commercially would not be in our interests right now.”

According to Open Electricity, the Kurri Kurri power station has been switched on only once in the past month, and has rarely been used since the gas component was commissioned, operating at a capacity factor of just 1.3 per cent – which is not unusual for a peaking power plant.

As Snowy Hydro explains in its latest media release, Kurri Kurri is expected to run “only on those occasions when electricity demand is high and renewable supply is limited.” It says it will operate using gas as its primary fuel, with diesel being used as a backup only when required.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Chickens “coming home to roost” for next Victorian energy minister, whoever it might be

The coming three years will be exceptionally tough for Victoria's next energy minister, experts say.

28 October 2026

World’s biggest battery maker snags deal for new Australian project, sees “huge interest” in sodium tech

China battery giant reveals it has been selected as the tech partner for a major…

28 October 2026

Victoria Coalition promises quick review of transmission plans, as it soft pedals stance on renewables

Victoria's likely next energy minister seeks to woo clean energy summit, promising quick fire review…

28 October 2026

Andrew Forrest’s Fortescue signs first 3rd party supply deal for its giant Pilbara “green grid”

Andrew Forrest's Fortescue signs up owner of huge lithium mine as the first customer of…

28 October 2026

Wind and solar projects to be given revenue certainty in new market design to back 75 pct renewables target

Updated: A simplied version of the new national policy mechanism will be used to propel…

28 October 2026

WA wants more renewables, but that does not mean it needs more gas

W.A. should easily meet its 75 pct renewables target, but there is a big question…

28 October 2026