CleanTech Bites

Snowy’s delayed gas plant finally enters grid system, as Forrest closes in on gas import terminal

Published by

The federal government owned Snowy Hydro has finally entered its controversial Kurri Kurri gas plant into the market operator’s grid management system, nearly two years after its original timeline and after an explosion in costs.

The milestone was noted by GPE NEMlog’s Geoff Eldridge, who says that the 660 MW facility is now registered in the Australian Energy Market Operator (AEMO)’s market management system, a precursor to the start of testing and commissioning.

As Eldridge notes, the gas-fired power station was first announced in 2021 by then federal energy minister Angus Taylor to support system reliability, and was originally intended to be built in time for the closure of the Liddell coal fired power station in April, 2023.

It was also designed to have a hydrogen component, but for the moment it is struggling to source even gas, and will have to rely on diesel generation while a 21 km underground gas pipeline is completed to link it into the main gas grid.

The wait may not have to be long, as the pipeline is due to be commissioned at the end of March, according to a new Australian Energy Regulator release which is deciding on whether to describe the new pipeline as a “transmission” or a “distributed” asset. It favours the former.

The gas turbines will act as peaking generators, boosting Snowy Hydro’s fleet of peaking generators, and its control over the “caps” market, which is a kind of insurance against the price spikes caused when such machines are switched on.

Ted Woodley, a former senior energy executive and critic of Snowy Hydro Kurri Kurri gas plant, and its Snowy 2.0 pumped hydro project, says the total costs of the Hunter Valley gas facility are now likely to be more than $ 2 billion.

The news comes as Squadron Energy announces that the landslide commissioning of its Port Kembla Energy Terminal, which will import LNG for use in Australia’s gas and electricity grids, has been completed.

The move comes amid controversy over the gas market – and whether the country, one of the biggest exporters of LNG in the world, should in turn import LNG, or set aside gas reservations, or open up more gas resources, to address shortfalls in its domestic market.

“PKET will deliver gas into the east coast market as we face structural gas shortfalls and also introduce much-needed competition, by unlocking significant and competitive international sources of gas that Australian doesn’t currently have access to,” Squadron said on LinkedIn.


If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Your support is invaluable. 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026