Grid access rules to be changed, but won’t penalise “advanced” projects that are ready to build

Published by

Victoria is offering a one-off, slightly easier process to a select number of developers when the state launches its new grid access regime next year — but only if they can prove they have projects are close to construction.

Vicgrid is changing how projects are allowed to connect to the state’s grid with a new network access regime from July next year, moving from the current National Energy Market (NEM)-wide open access and replacng it with a system that prioritises projects inside renewable energy zones (REZs).

But Vicgrid has had to address concerns that projects that are “well advanced” would have to compete with those that aren’t.

It has created a time-limited, one-off process for projects that have development approvals or a federal underwriting deal to win grid access under the new regime.

The Victorian grid manager, created five years ago to take over grid planning from the Australian Energy Market Operator, is preparing the ground for the Victorian Access Regime, the new framework for connecting projects to the grid, on the grounds that open access is creating challenges for developers in choosing where to invest and for communities through uncoordinated development.

The latest update refines the draft rules released in September last year, but with the proviso that actual regulations controlling the detail on how it will all work are still in the works, with a draft expected later this year. 

“Renewable development in Victoria needs to be well managed so we can deliver the new energy sources we need in a way that minimises impacts, treats communities with respect and creates real benefits,” said Vicgrid CEO Alistair Parker in a statement.

“The Victorian Access Regime will help us focus development in the right places and give developers inside renewable energy zones certainty their access to the grid won’t be impacted in the future by projects outside the zones.

“Under this new regime, all developers, whether they are inside or outside a zone, will be required to demonstrate how they will meet government expectations on community engagement and benefit sharing as a condition of being granted access to the grid.”

Third way for “advanced” projects

After July next year, projects inside Victoria’s REZs get priority via a competitive access process, and those outside have to go through the alternate Grid Impact Assessment (GIA) pathway to make sure they don’t take up network space prioritised for REZs. 

But Vicgrid’s one-off third way for advanced projects will look after those with a grid connection letter and either state planning approval or a federal environmental approval, or a Capacity Investment Scheme (CIS) contract. 

It will be the same competitive application process as under the new renewable energy scheme (REZ) process, but with a shorter window and it will apply across the state. 

The idea is to minimise the impact of the change on projects that have been built around the current open access arrangements.

However, there’s still work to be done to figure out how these projects will be assessed to make sure there’s still enough grid capacity for projects under the full new regime.

The CIS winners are creating a dilemma; they’ve already gone through a competitive process to win their underwriting agreement, but many mainly wind projects are struggling to progress. 

Vicgrid is planning to put them through a separate course, looking only at differences to the original CIS submission and progress to date – with a warning that those which aren’t on track to meet the 2030 deadline may not pass the new threshold.

“This assessment approach seeks to reduce duplication across competitive processes,” the Vicgrid update says. 

“It is anticipated that CIS projects will be granted access authorities, unless there have been significant deviations to the deliverability of the projects, or a failure to adhere to commitments made.”

Wind energy projects have struggled to get going, largely because of rising costs, transmission delays and the inability to seal significant off-take deals with the country’s big four gentailers and other corporate buyers.

Last week, energy minister Chris Bowen said CIS contracts are not open to renegotiation, but developers are welcome to withdraw and then bid again with the new economics.  

Gas is out, batteries are TBC

What Vicgrid is yet to work out is how to treat generation that is backed by batteries, or batteries by themselves. 

Right now, hybrid projects with both generation and battery storage are set to be assessed inside REZs in the same way as any generation project. 

But Vicgrid is still considering how hybrids will impact on REZ access limits, proposing an assessment based on the generation element’s nameplate capacity. 

“VicGrid is proposing that stand-alone storage projects, regardless of location within or outside of a REZ, will be subject to the GIA,” the Vicgrid update says. 

“In response to feedback… VicGrid is considering an alternative modified [GIA] assessment. 

“The next iteration of the draft GIA Guidelines will detail the proposed approach for consultation.”

The update also firmly closed the door on REZ access for hydro, and any non-variable renewables technologies including gas, oil, waste and coal.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, you can click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

CIS bakes in First Nations equity, revenue sharing deal for next renewables and storage tenders

Capacity in upcoming renewable and storage tenders under the CIS to be reserved for projects…

7 July 2026

Renewables remain cheapest new power option, and avoided $US480bn in fossil fuel costs in 2025

Renewables described as not only the cheapest new power source around the world, but also…

7 July 2026

Network owner says it sought to wind up leading renewable retailer due to outstanding debts

Network owner says it pursued winding up of Zen Energy due to outstanding debts, as…

7 July 2026

Construction ready, CIS-winning solar and battery hybrid project sold to Swedish developer

One of the biggest solar and battery projects Victoria has been sold to Swedish renewables…

7 July 2026

One Nation MP sponsors petition to sink sheep farmer-led solar and battery project

Farming family wants to host solar and battery project to underpin and co-exist with farming…

7 July 2026

Regulator bans another company from energy upgrades program because of falsified photos

Regulator bans another company from state's energy upgrades program, because of falsified photos used to…

7 July 2026