Regulations cause dead spot in WA solar market

The WA solar market is being held back by regulations being placed on the industry by grid operator Western Power. The regulations are specifically affecting the commercial rooftop space, creating two effective dead spots.

While the residential rooftop solar market in Western Australia is well established, with newly-merged utility Synergy reporting that around 2,000 solar arrays are being connected to the grid each month, the commercial rooftop market is still in its early stages. However, with some small and middle sized enterprises (SMEs) paying big prices for electricity, and taking into account the state’s prodigious sun, the potential of solar to supply these businesses is huge.

Unfortunately the market is not opening up as many solar business had hoped, with grid operator Western Power introducing regulations that have effectively put a stop to installations between 30kW and 60kW and then again between 150kW and 400kW.

“What we’re seeing is that customers will approach us with a problem around electricity spend, we will then go and recommend a solution,” explains Infinite Energy’s Managing Director Aidan Jenkins. “What we find is that in those dead spots, the financials don’t work.”

Solar arrays up to 30kW in capacity in WA can be connected to the grid through a “fast track” process, that effectively allows the installation to be approved and carried out with a minimum of fuss. However once an installation exceeds 30 kW, Western Power requires that the installation doesn’t feed any electricity into the grid – known as preventing reverse power.

The problem with preventing reverse power is the power quality relay and reverse power prevention system components add considerably to the cost of the installation. The Business Manager with Avant Solar, Ian Milne, estimates that the additional equipment required costs around $12,000, with between $10,000 and $20,000 added in providing the engineering services and documentation related to this, as required by Western Power.

It’s worth noting that every potential application is assessed individually by Western Power and whether the installation is to take pale on the high or low voltage grid plays a role in the protection required by grid operator.

While grid operators in some parts of the world are becoming more familiar with facilitating the installation of medium-sized installations onto the grid, it seems in WA, things are actually getting more difficult for the solar industry. In the last six months a further requirement has been placed on developers of solar projects in the commercial rooftop space.

Western Power is additionally requiring all installations which wish to export electricity to neutral voltage displacement equipment (NVD), on the network side of an installation. As the equipment is required on the grid itself rather than the installation, only Western Power is able to carry out the required works, with costs in the order of $50,000.

“The problem (when an NVD is required) is that only the network operator can provide the solution, for a fixed charged,” says Infinite Energy’s Jenkins. “So there’s not a lot of flexibility

there.”

Infinite Energy’s Jenkins reports that both the Sustainable Energy Association (SEA), located in Perth, and the Clean Energy Council have vocal in their opposition to the Western Power regulations that have hamstrung the commercial rooftop solar market segment in WA. Jenkins says that little progress has been made as yet and that the solar industry’s current strategy is to focus on reducing the cost of compliance.

One strategy employed to date by some West Australian solar developers, to circumvent the commercial rooftop dead spot, has been to overload inverters. This essentially means attaching a 40 kW array of modules to a 30 kW inverter – therefore avoiding Western Power’s regulatory hurdles. With a split east-west orientation, Milne from Avant Solar says that peak power output is avoided.

However, even here regulations appear to working against the West Australian solar industry. A relatively new Australian standard for solar, AS5033, requires that an inverter must have at least 75% of the capacity of the module array.

“There’s not scope to say, ‘I’ve got an east – west split, I will never reach peak, so I can go a little bit further,’” says Avant’s Milne, “the standards prohibit it.”

Western Power has reported to solar developers that it is currently working on an online portal through which grid connection applications for commercial rooftop PV systems can be applied. This may reduce the “soft” costs currently holding commercial rooftop PV back WA, however there is considerable scepticism amongst developers as to whether this will eventuate.

Comments

4 responses to “Regulations cause dead spot in WA solar market”

  1. Chris Fraser Avatar
    Chris Fraser

    By nature i am suspicious of things that prevent modernisation, but i would be interested in Western Power’s reasons for this as advised by them on RE. The idea of avoiding voltage anomalies in the network is a prudent one, but it would seem better to apply a network charge, that would permit investment to allow embedded generation to be distributed around the network and consumed before additional energy is dispatched from a central generator. Incumbents think “whoa – this would not be better”… So what do these new measures ultimately mean ? Investment will go into on-site storage instead.

  2. Chris Drongers Avatar
    Chris Drongers

    Good Lord! A government-owned agency operating in an oversupplied electricity market supported by long-term capacity supply contracts and with a risky distribution network wants to restrict distributed generation that would reduce profits and capacity to pay for redundant generation assets and replace crappy distribution assets and pay dividends to government? Can Jonathon comment on how receptive Western Power has been to edge-of-grid PV systems of significant size and how effective WP has been in recruiting demand management services into the existing grid please?

  3. Sean Avatar
    Sean

    build a 30 kw grid tie inverter system, then an ‘X’ kw UPS setup, solar array feeds a small bunch of batteries, which is also fed to a lower voltage by a mains powered battery charger, both are used by an inverter which supplies the entire business, and then bypasses the UPS system at night.

    This results in a small daytime uninteruptable supply, gives the power company an almost identical load profile, but complies with the rules. it costs a bit more, and is a bit less efficient, but is probably still cheaper than the grid price.

    alternatively, create multiple 30kw inverter systems on different connections.

  4. Shtoney Avatar
    Shtoney

    Spot on Jonathon, a year on and this is still a painful barrier from Western Power.

Get up to 3 quotes from pre-vetted solar (and battery) installers.