Major 200MW + battery solar farm approved in outback South Australia

The Lead

One of the largest photovoltaic solar farms in the Southern Hemisphere has been approved to be built in South Australia.

Work is expected to begin on the Solar River Project in early 2019 with completion of the 220MW PV array and 120MWh lithium-ion battery in Stage 1 planned for the end of that year.

Stage 2 – with a minimum of 200MW of generation and a 150MWh battery – is planned to begin construction in early 2020.

Solar River secured the land, about 150km north of the South Australian capital Adelaide, and received final development approval this month.

The Stage 1 array with single axis tracking will measure 3200 metres x 1800 metres and will be connected to the national grid by a transmission line to a substation near Robertstown, about 30km to the southwest.

The project is not reliant on grants or government support and will be 100 per cent privately funded through a mix of local and international investment.

Solar River Managing Director Jason May said the first generation from the site was expected in September 2019.

He said some of the energy produced would be contracted and some sent to the market for purchase by the retailers.

“Obviously there’s a fair bit to do in Stage 1 – there’s transmission lines and buildings to be constructed but the intention is to have everything finished by Christmas next year and then the main contractor will remain on site to continue with Stage 2,” May said.

“Really we just needed final approval and now the gun has been fired as it were so we’re making preparations to mobilise the main contractor and they’ll start advertising for jobs later this year.”

The solar farm will use a “cookie cutter” approach where sections with 5MW of PV are connected to a 5MW inverter that feeds in to a central inverter.

“They are all daisy-chained together by high-voltage cable and connected to the transmission network,” May said.

“The configuration of batteries and storage and photovoltaics to firm up electricity supply effectively acts like a baseload generator so it’s a little bit unique in that regard and we see it as the way forward for the industry.”

The Solar River project is proposed to be built about 30km northeast of Robertstown in South Australia.

May said the main purpose of the project’s grid stabilisation storage system and battery were to address intermittency issues sometimes faced by renewables.

“We can use the battery for those spot trading events when the price goes very high but our preference is to utilise it on a contracted basis to firm up our output to our longer term customers,” he said.

“The days are quickly disappearing where batteries are being used for those opportunistic revenues – their real place in the industry is to firm up renewables and the investors acknowledge that as well.”

The project, on a 5300ha piece of Australian Crown Land, is expected to create 350 regional jobs in the two-year construction period and 45 ongoing jobs for the 25-year life of the project.

South Australia leads the nation in the uptake of wind energy and rooftop solar with renewable sources accounting for more than 40 per cent of the electricity generated in the state.

However, the closure of two coal-fired power stations in recent years has increased the state’s reliance on energy supplies from the eastern Australian states, particularly in times of peak demand.

South Australia is also home to several globally significant renewable energy projects including Tesla’s “world’s biggest battery”, which was commissioned at Neoen’s Hornsdale Wind Farm in the state’s Mid North last year, and SolarReserve’s proposed 150MW solar thermal plant Aurora.

The Solar River site is less than 50km west of the proposed Lyon Group solar farm, Riverland Solar Storage, which is set to have 240MW of generation and 400MWh of storage.

Both sites are north of Goyder’s line, which separates what is considered land suitable for agriculture from the more hostile, arid outback.

May said the land just north of Goyder’s line was ideal for solar production because it was affordable yet still relatively close to the energy grid.

“South Australia is very rich in wind and solar resources – we have an enormous amount of it and it’s a free fuel if we choose to utilise it,” he said.

“We’ve got the technology to utilise it so let’s produce cheap electricity and sell it everyone who is connected to the network, which is the entire eastern seaboard.”

This article was originally published on The Lead South Australia. Reproduced here with permission. To read the original version, click here.

Comments

12 responses to “Major 200MW + battery solar farm approved in outback South Australia”

  1. Jon Avatar
    Jon

    It’ll be interesting to watch the power prices in SA with some tracking solar in the mix, especially with battery smoothing.
    Although S.A. Has some impressive RE numbers they’ve had all their eggs firmly in the wind basket so pretty exposed when wind generation is down.

    1. Matt Avatar
      Matt

      Pretty amazing to see the wind though. A few weeks ago there were something like 5 day straight where wind was at 1 Gw+ non stop.

      1. Alastair Leith Avatar
        Alastair Leith

        And then days without any which even storage limited by economics can’t cope with, solar from this and other projects, and Aurora will start to even out supply.

      2. rob Avatar
        rob

        Matt right now 135 NEM time on Tuesday S.A. is running on total renewables! Go us!

  2. Ian Avatar
    Ian

    Goyder’s line: farmers loss, and solar’s gain, and at Port Augusta, so close to major energy infrastructure. If you head a little inland from that town you would encounter The Olympic Dam and a bunch of other mines all ripe for solar and battery electricity supply..

    Can anyone say what happened to the Ceres wind farm that was planned for the York peninsula?

  3. phillyc Avatar
    phillyc

    Excellent. Keep the projects coming. Especially those with storage. Having tracking and storage will make for a fairly firm output. Interesting to note that they don’t believe that the battery will be used for profiting from market peaks which suggest they know that renewables and batteries are keeping a lid on price spikes.

  4. Tim Buckley Avatar
    Tim Buckley

    Great to see investors lining up for renewable energy infrastructure in Australia, almost despite the policy risks involved. Having a sensible national electricity policy would ensure a low cost, more sustainable and less polluting generation fleet able to deploy modern technology so as to compete in the current century. Instead, we have the entirely compromised NEG, the fifth best solution (out of five), well behind on delivering the policy certainty the Turnbull appointed Finkel review was meant to provide. One day we might get an energy policy designed to help the people of Australia, rather than a Luddite designed coal support scheme.

    1. Alastair Leith Avatar
      Alastair Leith

      What do you think is holding investors back in WA? A pro-renewables Govt policy vacuum? Synergy market dominance?

      1. Tim Buckley Avatar
        Tim Buckley

        A vertically integrated power system is one constraint. A relatively small grid load another. A government waiting to see the outcome of the NEG. Horizon is doing a lot of diesel replacement in non-SW WA microgrids, that is for sure. CWP Renewables is looking at a $20bn 9GW renewables project proposal in the Pilbara, with 1/3 focussed on domestic mining and ore processing electricity supply, so there are some developments.

        1. Alastair Leith Avatar
          Alastair Leith

          Yes Horizon seems to be the more future oriented of the big three GTEs and interestingly Horizon are triple vertically integrated so can sort the whole solution without getting blocked by another SOE or Govt Trading Enterprise as they’re known. It’s seems there are major points of contention between Synergy and Western Power, for example Synergy resisting WP desire to be able to add storage to the grid* or lease PV to residents.

          * exception being their cooperation on a joint venture microgram with storage for a new suburb

  5. Alastair Leith Avatar
    Alastair Leith

    “The solar farm will use a “cookie cutter” approach where sections with 5MW of PV are connected to a 5MW inverter that feeds in to a central inverter.”

    why would you invert a voltage twice? perhaps means from multiple inverters to a transformer to shift the voltage up? or power control circuits?

  6. Treble Sketch Avatar

    Another exciting new project in the works in my state! Pretty exciting to see more projects in the future! 😀

Get up to 3 quotes from pre-vetted solar (and battery) installers.