Swedish renewables developer OX2 has “substantially” scaled back the number of turbines it proposes to install as part of a massive wind and battery project north of Perth in Western Australia, in revised plans referred for regional development approval.
In planning documents submitted to the Shire of Dandaragang, OX2 says its Dinner Hill Wind Farm Project now proposes to install up to 131 wind turbines with a total generation capacity of up to 943 megawatts (MW), down from 170 turbines and 1.2 gigawatts (GW).
The proposed battery energy storage system (BESS) would have a capacity of up to 300 MW, as was initially proposed, but with between 4-8 hours of storage duration, instead of just four.
In a separate update published by OX2 last month, it said Dinner Hill would “likely include an ancillary battery energy storage system (BESS) to support the wind farm and discharge clean energy when it is needed most,” but that the size of the BESS would be confirmed pending further technical assessments.
OX2 says the changes to the wind turbine numbers and layout were informed by “extensive consultation” with landholders, community members, Traditional Owners, local government and government agencies.
“Community feedback, technical investigations and environmental assessments have informed substantial design refinement since acquisition by OX2 …significantly reducing impacts on native vegetation, Carnaby’s Black-Cockatoo habitat, farming operations, Aboriginal Cultural Heritage, bushfire risk and electromagnetic interference,” the documents say.
“Comprehensive technical assessments indicate that potential environmental, social and planning impacts can be appropriately avoided, minimised or managed through the proposed design, mitigation measures and ongoing management framework.”

OX2 – which is backed by a global private equity firm closely tied to Sweden’s powerful Wallenberg family – announced late last year that it had taken formal ownership of the Dinner Hill Wind Farm, alongside the Harvest BESS, the name of the project’s battery, from an unnamed WA-based developer.
The wind farm and battery are proposed for construction around 200 km north of Perth on predominantly cleared agricultural land across various private landholdings in the Hill River and Badgingarra townships around 26 km north of Dandaragan and 25 km east of Jurien Bay.
The total project area is approximately 30,024 hectares, while the actual development footprint sits at around 933 hectares – less than 5 per cent of the total project area.
OX2 says it consulted with host landholders to ensure farming activities could continue alongside the project, to provide supplementary income for local farmers hosting wind turbines.
OX2 is also proposing a community benefit framework which includes a neighbour benefit framework, Community Benefit Fund (CBF), and benefit sharing with the Yued People community “to ensure benefits are shared in the wider community over the life of the project.”
If you would like to join more than 28,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.