Home » Press Releases » Kidston solar project takes first delivery of modules

Kidston solar project takes first delivery of modules

Solar panels stored on laydown area.

PRESS RELEASE

Genex Power Limited (ASX: GNX) (Genex or Company) is pleased to provide shareholders with this latest update regarding the construction program for the Company’s Phase One 50MW Kidston Solar Project (KSP1 or Project).

Genex advises that the construction of KSP1 continues to remain on time and on budget for first generation in Q4 2017 and Practical Completion in Q1 2018. Key activities since the last update (refer ASX announcement 20 April 2017) include:

  •   First delivery of First Solar Thin-Film solar modules complete;
  •   First delivery of NEXTracker components underway;
  •   Piling rigs mobilized to site ahead of pile delivery;
  •   Ergon switchyard equipment 75% installed and equipment earthing underway;
  •   Solar farm substation earth-grid installed;
  •   Laydown area for materials storage and component assembly 100% complete; and
  •   Site clearing approximately 90% complete.
Solar panels stored on laydown area.
Solar panels stored on laydown area.

Commenting on the recent progress of KSP1, Managing Director of Genex Power Michael Addison said, “Genex’s focus on project delivery continues with the project continuing to perform to budget. Kidston is now a hive of activity with 65 people employed on site. The outlook for wholesale electricity and Large-scale Generation Certificates (LGCs) remains robust which underpins the potential to deliver strong cash flows to Genex”.

The Federal Government, through the Australian Renewable Energy Agency has provided $8.9 million funding to support the construction of the $126 million Project at Genex’s Kidston Solar Farm.


CONTACT:

Simon Kidston

Executive Director
Tel: +61 2 9048 8852
Email: [email protected]

Get up to 3 quotes from pre-vetted solar (and battery) installers.