Home » Commentary » Solar Oasis sets out to bust some solar myths

Solar Oasis sets out to bust some solar myths

Whatever anyone thinks of the technology – and no one will really know until it is deployed and operating at a commercial scale – it is clear that the Solar Oasis consortium behind the 40MW “big dish” solar thermal plant planned for Whyalla are taking an innovative approach to financing and to the energy markets in general. And energy retailers and aspiring solar developers should probably take note.

RenewEconomy caught up with Alex Braisier, the managing director of Solar Oasis, by phone on Wednesday while he was in China, where he is negotiating supply and financing deals for the project. That was our first takeaway from the chat: the $230 million project will not be financed by Australian institutions, as had been envisaged originally, even though an in-principle arrangement had been made with ANZ. Braisier says Australian institutions are too inflexible and narrow in approach.

Instead, Braisier will source equity partners and debt finance mostly from China, possibly from suppliers and other interested parties. “Working with vending project financing arrangements in China is more imaginative than going through motions with an investment bank in Australia,” he says.

(This is not surprising. The fact is that Australian institutions have no experience with such technologies and no reference points. International banks are expected to carry much of the load, and the inspiration, for the solar flagships projects. As this article points out, however, the loan guarantee program in the US has helped financiers get comfortable with the technology and bring down the cost of financing. And check out this article on Forbes, about how investors are making big money from renewables. There are lessons here for the Clean Energy Finance Corp.)

The relationship with Chinese partners and suppliers has grown since Braisier first formed a partnership with Chinese-based solar PV manufacturer SunGen, which is linked with an energy retailer in Braisier’s stable, Sanctuary Energy, supplies its PV modules (at zero upfront cost) and has taken a 26 per cent stake.

Sanctuary is a specialist in green energy retailing, and has some 20,000 customers, mostly with rooftop PV of between 1.5kW to 10kW, and solar hot water systems, with an aggregate capacity of around 30MW. It is small and also nimble: Braisier and his partners are former energy traders, and have developed a solid business playing the market, hedging with caps and derivatives, and using the natural advantage of solar that produces energy in the shoulder and high peaking periods.

This leads us to the next interesting point: the proposed PPA for the Whyalla project, which will feature 330 “big dishes” first developed by ANU and then taken up by Wizard Power. (It is solar thermal with a design change, instead of parabolic troughs or flat mirrors, or solar towers, these dishes can generate temperatures of 2000°C – more than you need unless you are trying to crack hydrogen or turn coal into liquids. So around 600°C will do for Whyalla).

Anyway, Braisier sees the solar dishes as “peaking power,” and he will treat the plant as such. He shakes his head (I presume, it was over the phone) at the reported attempts by the Solar Dawn consortium to strike a PPA of around $200/MWh, in which they were unsuccessful. Why treat solar thermal like a coal-fired power station? he asks. It should be treated like a hydro or gas-fired plant, none of which are ever built with PPAs in hand. They simply play the market and sell into the peaks, when prices jump.

“It (the PPA) will be a derivative product – it’s a peaking plant,” Braisier says. “ “It will sells caps and derivative product to help retailers manage risk. That’s what solar thermal will do.” And given that South Australia has highly volatile prices, and its big peaks coincide with hot sunny days, Braisier can be certain that the Big Dish array will be producing energy when it is most needed, and most profitable. The Solar Oasis offtake agreement will be done through Sanctuary Energy.

“I think we have a different view of the market, we don’t have 100 per cent hedges, and we can take an innovative approach,” he says. “You don’t bank a hydro plant in Australia, or even a gas plant – they are not positioned in market as base-load plants. To suggest that a solar thermal behaves and looks like a coal-fired plant is ridiculous.”

Braisier says the consortium is not planning storage, but may consider adding a small gas-boosted generator to help in firming and dispatchability into the peaks, which he says would improve the project’s IRR. It is also talking, with SunGen, about the possibility of installing a 5MW solar PV installation.

Braisier’s company is currently working with SunGen to construct several solar PV installations of between 1MW and 10MW in the Philippines, replacing diesel, which is costing up to $600/MWh or more. He says PV plants of that size can be installed for around $200/MWh.

Braisier expects the nominated $230 million cost of the project will fall too. Since the tender was first accepted in 2009, the market has changed dramatically, and the price of power blocks, for instance, was down by around 30 per cent. “Vendors are falling over themselves to provide vendor financing,” he says. “We expect a significant reduction in costs.”

Now that the funding deed has been signed, Solar Oasis will work on final design, permitting, and arranging grid connection. Construction is expected to start in May next year, with the project completed before the end of 2015. It will be interesting to see which project provides electricity to the grid first – Solar Oasis, or the 250MW Solar Dawn project in Queensland.

Comments

6 responses to “Solar Oasis sets out to bust some solar myths”

  1. D. John Hunwick Avatar
    D. John Hunwick

    great news indeed. Solar power at 2000 degrees – at last it can be used for nearly every process going around. Is there any chance that the position South Australia fins itself in with strong government support for solar will wash off on to Mr Abbott and the whole of Australia can at last get on the front foot? I hope so. PS for the technically ignorant what are PPA and IRR?

    1. Tony Avatar
      Tony

      PPA – Power Purchase Agreement – an agreement to buy power from an electricity producer.
      IRR – Internal Rate of Return – Financial performance of the investment.

  2. Petra Liverani Avatar
    Petra Liverani

    Solar thermal may not be positioned in the market currently to provide baseload power (it’s hardly in the market at all in Australia), however, Concentrated Solar Thermal Power with molten salt storage (CSP+) can indeed supply baseload energy 24/7, or even better, dispatchable power which better matches demand load. Go to http://www.beyondzeroemissions.org and download the Stationary Energy Plan which explains how Australia could be powered by 60% CSP+ and 40% wind in 10 years. To see 24/7 CSP+ in action in Spain go to http://tiny.cc/0jahy.

  3. Michael Avatar
    Michael

    “It is solar thermal with a design change”

    For Whyalla, are they producing steam for a turbine ? or running stirling engines ?

    1. Ian Avatar
      Ian

      Both concepts utilise a steam turbine. Stirling engines are not as reliable and cannot produce large amounts of output from a single unit. The high temperatures created in this system suit themselves to backpressure + condensing or hybrid turbines (prob 10-20MW ea). Typically a triple cycle steam turbine system is possible to extract a maximum amount of energy from the system (>40-60%), although I expect that the designers will stick to a double cycle system. The challenge in Whyalla is finding a suitable cooling medium to bottom the cycle. The next challenge is to have a steam system design that can cope with the high pressures and thermal cycling and dealing with the corrosion issues associated with steam systems that aren’t in constant operation. Anyone who has dealt with high pressure steam systems will tell you that transients in steam systems cause all sorts of leaks in flanges and valve packings. Great care will need to be given to the installation and maintenance of steam traps in the system. What is interesting is that Wizard are now talking about molten salt after all of the initial fanfare of a catalysed Ammonia cycle.

  4. Ian Avatar
    Ian

    It is good to see that this project is finally moving forward. It’s a pity that we’re left to foreign investment (esp China) to take the risk on the capital raising as we are at risk of losing the technological ownership to OS AGAIN! There are a number of technical hurdles to overcome with this technology, not limited to whether any side reactions occur over the catalysts and how to purge or convert these reaction products/corrosion products. Also, good luck on sourcing any gas from the Whyalla for a turbine as an improvement on IRR.

Get up to 3 quotes from pre-vetted solar (and battery) installers.