World’s tallest wind turbine faces key construction test with 300-metre nacelle and blade lift

Published by

The construction of the world’s tallest wind turbine in eastern Germany faces a decisive step on Sunday 20 September, when the nacelle and rotor blades will be lifted to a height of 300 metres if weather conditions permit the operation, reports t-online. 

Including the blades, the wind turbine in Schipkau, in the eastern state of Brandenburg, is set to be 365 metres tall, almost exactly the same height as Berlin’s iconic TV tower. Schipkau lies roughly 115 kilometres south of Berlin.

Higher wind speeds and better distribution at this altitude will allow more full-load hours, according toproject developer Gicon. Founder Jochen Großmann has previously argued that conditions are comparable to offshore wind turbines, but with much lower onshore construction and maintenance costs. 

Taller turbines are widely seen as key to unlocking more onshore wind capacity in many countries including Germany, where suitable sites are limited. Gicon has said high-altitude turbines could eventually be deployed in low-wind regions that have so far not been economical for wind power production.

Following measurements on a 300-metre-high tower at the same site in the lignite mining region Lusatia, Gicon said the height will increase wind energy yield by 40 percent, which equates to twice as much electricity yield with the same rotor diameter. The wind turbine features a design involving a lattice structure with four legs, reminiscent of electricity pylons and the Eiffel Tower in Paris. 

If everything works according to the plans, a crane will lift the nacelle, rotor hub and blades onto a platform at a height of 165 metres, the article says.

Once everything is assembled, the entire structure – which will weigh 750 tonnes including a movable inner tower – will be moved upwards using a hydraulic lifting system more commonly used in heavy-duty logistics and bridge construction.

This complicated process is necessary because the destination at a height of 300 metres is out of reach for cranes.

The project is attracting much international interest, with Chinese and Indian delegations visiting the construction site, the article said.

Clean Energy Wire. Reproduced with permission.

Share
Published by

Recent Posts

Solar and battery micro-grids get funding boost for remote communities in wake of Broken Hill blackout

Plans for solar and battery microgrids in remote communities gets funding boost in wake of…

15 September 2026

Underwater solar cells shown to generate power from 10 metres beneath the South China Sea

A team of Chinese and Swiss scientists has achieved the first functional validation that solar…

15 September 2026

Labor puts key but contested transmission line on hold until after state election, pending cost review

Updated: Victoria premier puts key transmission link on hold pending cost review, and promises no…

15 September 2026

Coalition vows to “go after gas” as it suggests “massive corruption” in renewables build-out

Coalition vows to"go after gas" and alleges massive corruption in renewables industry as party energy…

15 September 2026

“Why Whyalla and not us?” Recyclers say government backflip will trash millions invested in their industry

It may come down to who you know. Recyclers wonder why the government poured money…

15 September 2026

Trump’s EPA predicts coal generation to increase 10-fold after gutting greenhouse gas limits

US EPA guts greenhouse gas limits of coal and gas fired generators, and says it…

15 September 2026