Wind turbines completed at ground-breaking W.A. gold mine microgrid

Published by

The last of five wind turbines has been installed at the Angew gold mine in Western Australia – Australia’s first mining sector project to use wind power as part of a large hybrid renewable microgid.

The five 3.57MW Goldwind turbines make up one component of the ARENA-backed microgrid project that is being developed and operated by EDL under a 10-year agreement to supply power to the Agnew gold mine, which is owned by the company Gold Fields.

As One Step Off The Grid reported in December of last year, the huge turbine parts, including 60m blades, made a 630km road trip from Port Hedland to the mine site, in what was believed to be the longest such truck-trip for components of that size in the world.

Goldwind said on LinkedIn last week that the final turbine had been successfully completed, adding 17.85MW of wind power capacity to the mine’s existing 23MW solar, gas and diesel power station, and a 13MW/4MWh battery control system under construction.

Once completed in mid-2020, Goldwind says the the Agnew Hybrid Renewable Project will have a total installed generation capacity of 54MW, with renewables supplying more than 50 per cent of the mine’s power requirements.

Source: Goldwind LinkedIn

In comments in November last year, Gold Fields executive vice president Stuart Mathews said he hoped the project would lead to more and more mines integrating renewables into their power supplies.

“This is a significant milestone for both the Agnew gold mine and the broader Gold Fields Group, demonstrating our ongoing commitment to strengthening our energy security, optimising energy costs and reducing our carbon footprint through the adoption of new technologies,” he said.

“We are hopeful that this will also enable other companies to consider the options for decarbonising their operations.”

And consider it they have. Just last week Oz Minerals explained in its results briefing why it had decided to go with a combination of wind, solar and battery storage – over gas – to provide 80 per cent of the power needs of its proposed $1 billion nickel mine in a remote part of Central Australia.

As noted above, the Agnew project has received funding support from the Australian Renewable Energy Agency, which provided $13.5 million in recoupable finance.

To read the original story on RenewEconomy sister site One Step Off The Grid, click here…

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

CIS-winning wind farm finally starts construction, more than a decade after first unveiling

One of the first wind projects to win a CIS deal has finally begun construction,…

8 July 2026

Electric trucks, mines and farms, low carbon fuels key to break Australia’s foreign fuel dependence

Superpower Institute releases findings from study examining ways to improve Australia's fuel security in the…

8 July 2026

“They are losing patience:” Just one in ten investors believe Australia will meet renewables target

Investors buoyed by re-election of a Labor government last year are now downbeat, citing transmission,…

8 July 2026

CIS bakes in First Nations equity, revenue sharing deal for next renewables and storage tenders

Capacity in upcoming renewable and storage tenders under the CIS to be reserved for projects…

7 July 2026

Renewables remain cheapest new power option, and avoided $US480bn in fossil fuel costs in 2025

Renewables described as not only the cheapest new power source around the world, but also…

7 July 2026

Network owner says it sought to wind up leading renewable retailer due to outstanding debts

Network owner says it pursued winding up of Zen Energy due to outstanding debts, as…

7 July 2026