Why TRU quit geothermal – too risky, too costly

Published by

TRUenergy has justified its recent decision to back out of one of the most advanced geothermal projects in Australia, the Paralana joint venture in South Australia, saying it was too risky and required too much up front capital compared to other energy options.

The decision by TRUenergy to quit its share of the Paralana joint venture (which was announced just before Christmas but went barely reported) and leave Petratherm and Beach Energy as the sole remaining partners, means that all three of Australia’s big utilities have reassessed their exposure to the geothermal industry in recent years.

TRUenergy’s head of business development Ross Edwards told RenewEconomy in an interview this week that the risk profile and the capital requirements of the project were not as attractive as other options.

“We had a pretty structured option arrangement, where it had to meet the milestones to progress,” Edwards said. “And we had a lot of delays and a lot of challenges with those time frames. Some of that was weather and other things, but ultimately companies like Origin and Beach are drilling in oil and gas exploration and have that sort of risk appetite. Whilst we were keen to investigate and have a go if you like, ultimately as it progressed it no longer fitted with our risk appetite.”

TRUenergy announced in 2008 that it would commit to spend an estimated $57 million on the venture, which plans to build a pilot plant in 2013 and has won a $63 million grant from the Federal Government to build a 30MW demonstration plant which will provide energy to the Beverley Uranium mine.

TRUenergy would have earned a 30 per cent stake if it had spent the entire $57 million. In the end, it is thought that it only contributed $6 million towards drilling and stimulating the first and second deep wells, and sacrificed a 10 per cent equity stake by choosing to withdraw.

It would have earned a further 5 per cent equity by contributing $7 million towards the cost of developing a 7.5MW pilot plant to provide electricity to the neighbouring Beverley Uranium Mine, and a  final 15 per cent for by contributing $44 million towards the development of the 30MW demonstration plant Stage. This would be sufficient to power Heathgate Resources Beverley mine and its proposed mine development at the nearby Four Mile deposit.

Its withdrawal follows the decision by AGL Energy to quit the Parachilna project with Torrens Energy in 2010, and Origin Energy’s decision last year to write off $204 million invested in its joint venture with Geodynamics in the Cooper Basin. Origin, however, remains involved with that venture, which has resumed drilling at Habanero near the township of Innamincka, and is also exploring opportunities in shallower and possibly less technically challenging reserves known as hot sedimentary aquifers.
“I would concur with Grant King’s comments the other day that geothermal is still a great opportunity,” Edwards said. “But it takes a lot of money to invest, to progress and to understand the opportunity, and that’s going to take some time.”

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Women strongly opposed to nuclear power, just one in three men willing to live near one

Survey finds just 26 pct of women think nuclear power would be good for Australia.…

4 December 2024

Australia could build a $3 billion industry making hydrogen electrolysers, CSIRO says

New report by CSIRO suggest electrolyser manufacturing by Australian companies could be worth $2.9 billion…

4 December 2024

Two workers rescued from burning Siemens Gamesa wind turbine by helicopter

Two workers have reportedly been rescued by helicopter from a wind turbine in Brazil after…

3 December 2024

Japanese oil giant announces $200 million green hydrogen investment in Queensland

Japan’s largest oil company has announced a $200 million investment into Queensland’s green hydrogen ambitions,…

3 December 2024

Fortescue pauses Science-Based Target validation as rules around emission counts are reviewed

Fortescue suspends its validation work under the Science-Based Target Initiative while the tricky question of…

3 December 2024

Cyclone resistant Port Hedland solar and big battery opened to provide power to BHP port facility

The first cyclone resistant solar farm, along with a big battery, have been opened to…

3 December 2024