Fertiliser giant firms up first leg of Indigenous-backed, 1.2 GW green energy hub

Published by

A 50 megawatt (MW) solar project near Karratha will be the first stage of a massive 5 gigawatt (GW) energy vision, and will be built and operated by Western Australian chemicals conglomerate Perdaman.

The solar project will connect to the local grid, powering Perdaman’s nearby $4.5 billion Project Ceres urea plant on the Burrup Peninsula near the Pilbara town.

It’s expected to be connected to the urea plant by the end of 2027, with terms promised by the end of this year. 

It will also be the first project inside an up to 1.2 GW energy park being built by the Ngarluma Aboriginal Corporation (NAC).

The NAC energy park vision is to lease land it owns in the Pilbara to green energy developers, offering up acreage that already has unified land access, heritage, environmental approvals, planning and commercial pathways. 

The vision is being backed by the Western Australian government, which in December promised $2.7 million for the first of these hubs to fund surveys, approvals works, and technical activities over the next 12 months.

Ngarluma country stretches across much of the coastal areas in the western Pilbara region and includes the coastal towns Karratha, Roebourne, Wickham, Cape Lambert, and out to Whim Creek. The region is home to much of the Pilbara’s Industry including Rio Tinto Iron Ore, Dampier Salt, Woodside, Yara, and Perdaman. 

“Ngarluma Green Energy Parks will be a game changer for the fast and straight forward development of large-scale renewable projects,” Ngarluma green energy director Belinda Churnside said in a statement.

“It is 100 per cent owned and operated by NAC for the benefit of Ngarluma people. We very much appreciate the support and partnership we have with Perdaman and the state to help NAC activate the first green energy park as soon as 2027.”

A statement from WA energy minister Amber Jade Sanderson notes the Perdaman solar project itself will also connect to the Maitland-Karratha-Burrup transmission line, one of four corridors the Cook government is prioritising to speed up the decarbonisation of heavy industry in the north of the state through providing renewable energy sources.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Chart of the Day: Monster El Nino event smashes records as sea temperatures soar

Sea surface temperatures are now way ahead of previous levels at this time of the…

8 September 2026

Native forests “at a crossroads” as Greens wrestle with which way to turn on carbon credit plan

When Greens elder Bob Brown addressed a throng of forest campaigners on Saturday, he did…

8 September 2026

Australian renewables retailer and consumer energy pioneer hits the auction block

One of Australia's landmark renewable energy "gen-tailers" is reportedly up for sale, with its major…

8 September 2026

Batteries help cut solar curtailment in half, as PV output hits monthly record

Large-scale solar curtailment was "reduced significantly" in August as batteries help prevent electrons from going…

8 September 2026

“Serious impact:” Budget home battery brand faces suspension from rebate due to non-compliance

Seven home battery models from one of the up and coming new budget brands on…

8 September 2026

Rock lobsters and whales: First offshore wind project on west coast hits the EPBC queue

French energy giant seeks federal approval to start work on offshore wind projects in newly…

8 September 2026