Late last month, the Topaz Solar project achieved full commercial operation with the completion of its final 40-megawatt (AC) phase. This is the first 500-megawatt plus solar farm to come on-line in the U.S. and the largest solar plant on-line in the world.

Two years ago, the millionth First Solar (FSLR) solar module was installed at the power plant owned by MidAmerican Solar. As of today, the project has installed 9 million solar panels across 9.5 square miles in San Luis Obispo County on California’s Carrizo Plain. Construction began in 2012 and was expected to be complete in early 2015 — so call this an on-time delivery.

The solar farm was not the recipient of a loan guarantee and is built on “disturbed farm land” miles away from sensitive areas in the Carrizo Plain National Monument. First Solar suggests that the project will create $192 million in pay for approximately 400 construction positions over the three-year build and “$52 million in economic output for local suppliers.” PG&E will purchase the electricity from the Topaz project under a power-purchase agreement.

Information on the interconnection comes courtesy of the WECC website and the intrepid sleuthing of GTM solar analyst Cory Honeyman.

Followers of ancient history will recall that this project was originated by OptiSolar and that some of the Topaz real estate was once intended for an Ausra CSP solar power plant.

Here’s a chart showing the top three U.S. PV power plants under development in the U.S.

Project Name Developer Capacity (MWac) Capacity On-Line as of 11/14 State Offtaker Owner
Topaz Solar Farm First Solar 550 550 CA PG&E MidAmerican Energy Holdings
Desert Sunlight First Solar 550 524 CA PG&E, SCE NextEra Energy Resources, GE Energy Financial Services, Sumitomo
Solar Star  SunPower  579  309  CA  SCE MidAmerican Energy Holdings

Source:  GTM Research’s Utility PV Market Tracker

Check out the GTM Research Utility PV Market Tracker for much more information on utility-scale solar deployment in the U.S.

Source: Greentech Media. Reproduced with permission.

Recent Posts

Hunter Valley collieries to be greened-up as clean industrial hubs in “post mining land transformation”

State and federal governments aim for 7,000 green and industrial jobs under new master plans…

14 July 2026

“We cannot wait:” Changes made to renewable tenders to ensure wind and solar projects actually get built

Key changes have been made to renewable tenders to ensure that the winning projects can…

14 July 2026

Coal closure delays and soaring prices mean more batteries and fewer syncons to keep heartbeat of grid

Soaring syncon costs and supply issues, along with delays to coal closures, is opening up…

14 July 2026

Spitting chips: A deep dive into the data and token industry, and who carries the GPU risk

This note provides an estimate of demand and supply of tokens, draws a conclusion about…

14 July 2026

Wind project with an 8-hour battery hybrid looks for final green light after speeding through state approvals

A new wind-battery hybrid project speeded through state approvals, now it needs one more nod,…

14 July 2026

Graph of the Day: Half-time and hydration breaks lift grid demand in England and Norway World Cup game

England and Norway experienced big surges in demand during half time and hydration breaks in…

14 July 2026