Tesla Powerpacks arrive for next big battery at Victoria solar farm

Published by
Tesla batteries arrive at Gannawarra Solar Farm. Source: Lily D’Ambrosio, Twitter

The first of more than 400 Tesla Powerpack batteries have begun arriving at Victoria’s Gannawarra Solar Farm, as work gets underway on what will be one of the biggest solar and storage installations in the world.

The 60MW Ganawarra PV project in north-west Victoria – which was connected to the grid just under two months ago – is the first large-scale solar farm to be constructed and switched on in Victoria, and is jointly owned by Wirsol Energy and Edify Energy.

The batteries will make up the adjoining Gannawarra Energy Storage System – which will be a 25MW/50MWh Tesla Powerpack battery that will enable some of the solar plant’s output to be time shifted into the evening, or peak demand periods.

This battery – one of three to be installed in Victoria this coming year, two of them through the state Labor government’s energy storage auction – will be completed before the start of next summer, by December 1.

The output from both the solar farm and the battery storage installation are contracted to EnergyAustralia.

Mark Hogan, managing director of Wirsol, said in April that adding the Tesla battery storage system to Gannawarra would set a new benchmark for solar projects in Australia.

“The benefits of these types of projects will resonate with Australian consumers and the broader economy for many years,” he said.

The other big battery to be installed in Victoria under its recent auction will be an installation from Fluence at Ballarat, providing network services.

A third battery storage facility, to be built as part of the Bulgana energy hub that will include a wind farm and 20MW/34MWh of battery storage to power a new greenhouse near Stawell, will be completed next year. That, too, will be a Tesla battery.

And in South Australia, another big battery is also coming on line, with commissioning taking place now of the 30MW/8MWh battery at the Dalrymple sub-station, near the Wattle Point wind farm, to provide grid services and act as a renewables-based micro-grid in case of broader outages.

Note: To hear an interview with Angus Gemmell, of Solar Choice, who initiated the development of Ganawarra and several other big projects in Victoria and Queensland, please listen to our April 11 Solar Insiders podcast, which you can find here.

You can also listen to this latest Energy Insiders podcast which includes an interview with rival battery storage firm Fluence, and the plunging cost of solar and battery storage, and why they can beat gas generators as peaking plants.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: Governments

Recent Posts

Big battery owner slapped with hefty fine for pushing up power prices and “profit maximising”

State owned company cops hefty fine for "profit maximising" and electricity price "distorting," through battery…

3 September 2026

New solar farm connects to grid, part of state’s first PV-battery hybrid project

The solar component of what is likely to be the first PV-battery hybrid in Victoria,…

3 September 2026

Here’s how many wind and solar projects Victoria could stand to lose if VNI West is dumped 

Using loss factors and line congestion risk, we've tallied how far the damage will spread…

3 September 2026

Amazon inks its first ever standalone battery tolling agreement – with a project in Australia

Global web services giant signs its first ever standalone battery "tolling" agreement, globally, in a…

2 September 2026

“Bloody dangerous territory:” World on track to exceed 1.5°C warming

Earth is on track to exceed 1.5 degrees of warming within years, the United Nations…

2 September 2026

“Fully funded, fully contracted:” Construction team ready to go on state’s largest solar-battery hybrid

Frontier Energy says it has secured all major contracts to start construction later this month…

2 September 2026