“Fully funded, fully contracted:” Construction team ready to go on state’s largest solar-battery hybrid

Published by

Perth based clean energy developer Frontier Energy says it has secured all major contracts to start work later this month on the first stage of what will be the largest solar and battery hybrid on Western Australia’s main grid.

The Waroona Renewable Energy Project, which has giga-scale ambitions over the long term, will in its first stage co-locate a 132 megawatt (MW) solar farm with a 6.9-hour 81.5 MW battery.

The hybrid project, which will be built around 120 kilometres south of Perth, is designed to generate solar energy during the day and dispatch stored electricity into the grid during the evening peak.

Frontier Energy announced in July that it had locked in a complete funding package to finance the project, securing credit-approved commitments for project finance debt facilities of up to approximately $A280 million, including a construction facility of up to approximately $250 million.

Having evolved through several configurations during its development, the Waroona Renewable Energy Project has already secured both state and federal approvals.

The project also has an underwriting agreement under the federal government’s Capacity Investment Scheme, which acts as a “top up” should its other sales revenue fall below certain levels. The sum is not quantified, but if it is included in “other” in the graph above, then it is not significant.

The company followed up this week with the announcement that it had subsequently executed all major contracts for development.

Fixed-price contracts were secured for all major equipment and EPC works, including tier-one global suppliers such as Longi, which will supply solar panels, Trina Storage, who will supply battery storage systems, Nextpower, supplying solar tracker systems, and SMA Australia, which will provide the solar inverters.

EPC contracts have also been signed with Monford Group, and Western Power connection is now unconditional, enabling the export of up to 99 MW and import of up to 95 MW.

“This is a defining milestone for Frontier,” said Jamie Cullen, Frontier Energy executive chairman.

“We have now secured the full suite of contracts required to deliver Stage One at our Waroona Project and position the company as Western Australia’s largest solar-BESS hybrid power producer.

“The state needs new generation to support the targeted retirement of ageing fossil fuel plants while meeting rising demand from data centres and population growth,” Cullen said. “Stage One is our first step in delivering exactly that.”

Frontier says the longer-term plan is to add a second, third and fourth stage, taking the total project to around 1,000 MW and up to 660 MW of battery capacity.

“With only 300 of our 830 hectares of grid-adjacent freehold land committed to Stage One, the team is already advancing Stage Two,” Cullen said on Tuesday. “We are fully funded, fully contracted and ready to build.”

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

New CEOs at CS Energy, CER, Ark Energy and Western Power; new role and hire…

2 September 2026

Scrapping VNI-West will “guarantee a massive increase” in power bills, former energy minister warns

Scrapping VNI-West and other projects designed to support renewable energy will result in "massive" electricity…

2 September 2026

Fortescue green iron rival wins Arena cash to scale up Perth demonstration plant

Element Zero, the upstart Pilbara green iron contender and survivor of a legal challenge from…

2 September 2026

NSW opposition energy spokesperson announces retirement months out from state election

The New South Wales Coalition Opposition's energy and climate change spokesperson, has announced his retirement…

2 September 2026

State looks to tariff changes to help take the heat out of decarbonisation for big business

NSW is looking at tariff reform to encourage big gas users to switch to heat…

2 September 2026

Regulator “not satisfied” with Transgrid’s plan to recover transmission cost blowouts, but doesn’t rule it out

Transgrid might be able to claw back some of the more than $1 billion in…

2 September 2026