Sun Brilliance gets approval for WA’s biggest solar plant

Published by

A 100MW solar power plant in Western Australia’s Wheatbelt region has taken a significant step towards realisation after getting approval from the Mid-West Wheatbelt Joint Development Assessment Panel.

While the project’s initial timeline has slipped a little, it now appears likely Australia’s first “merchant” utility scale solar array will go ahead, although it will be competing against a rival plant in Queensland being developed by UK-based Eco Energy.

Aerial photo of Nyngan solar farm in NSW, which is 102MW

Perth-based developer Sun Brilliance confirmed the news last Friday, noting that the $160 million project will be a significant source of Large Scale Generation Certificates (LGCs) in WA.

The Mid-West Wheatbelt Joint Development Assessment Panel approved the plan at a meeting on November 28, with adjoining landowner Ray Lehman, and Sun Brilliance’s Ray Wills and Dilawar Singh answering questions posed by the panel.

The development group placed some conditions on the PV power plant and the proposed accompanying visitor precinct. These conditions include: that the project is developed within two years of the approval grant; that the electrical substation is relocated to a site at least 200 meters away from the nearest home; and that a detailed transport management plan be developed accounting for the construction period.

The 100 MW power plant will be located outside the WA Wheatbelt town of Cunderdin, 158 km east of Perth, at a property owned by Sun Brilliance known as Creswick. The plan is for sheep grazing to continue on the property at the same level as today, with the sheep reducing the need for for grass and weeds to be regularly cut as a part of scheduled plant Operations and Maintenance (O&M).

An advantage of the Creswick location is that it lies 2 km north of a 132 kV Western Power transmission line. Sun Brilliance will develop the 132 kV/22kV substation required.

“We have been very pleased with the professionalism of Western Power in their consideration of our project needs, and with just a few small variations on milestones, still within the framework of our original timeline,” said Sun Brilliance director Ray Wills.

Wills sits on the board of regional WA utility Horizon Power.

Sun Brilliance Chairman and CEO Dilawar Singh said that construction on the project is set to begin in April 2017, with the installation to be completed by September.

At the time of completion, the 100 MW project will likely be Australia’s largest by electricity production, when the effect of the single axis tracking system is taken into account.

The project developer must now finalise debt and equity financing and is aiming for a 70/30 split.

Recent indications are that funding conditions for large scale solar in Australia have improved rapidly recently, partly as a result of ARENA’s large scale solar scheme. The Sun Brilliance WA project did not apply for an ARENA grant.

Sun Brilliance is unwilling to provide further details on the progress it is making with its financing efforts, nor to the project’s revenue stream.

While it has fallen slightly in recent weeks, Green Energy Markets figures reveal LGCs are currently trading in the high $80/MWh range. The 100 MW project is expected to create 200,000 LGCs annually.

WA utility Synergy has developed very few renewable energy projects of its own in recent years, preferring to purchase certificates on the spot market – generally from solar and wind projects in the eastern states. RenewEconomy understands that WA Energy Minister and Treasurer Mike Nahan has instructed Synergy, which is state owned, to purchase LGCs locally, to encourage renewable project development in the state.

If Synergy comes to a purchase agreement with Sun Brilliance for the 100 MW project, it would significantly reduce the developer’s risk, with the electricity generated to be traded on the WA spot market.

The solar project is expected to create 150 jobs during the construction phase, and eight to ten full-time jobs during operation.

Sun Brilliance would not provide any details as to EPC arrangements nor to component suppliers. However, in its public presentation on the project it is revealed that it is considering both multicrystalline and cadmium telluride modules (CdTe) – with First Solar the only manufacturer with sufficient manufacturing capacity to supply 100 MW of CdTe panels.

Interestingly, the Sun Brilliance presentation notes that the warranted life of the project is 30 years. The warranty period indicates that dual-glass modules, where the foil backsheet is replaced by a second sheet of glass, are currently being considered by the developers. Glass-foil modules, the industry standard today, are issued with 20-year warranties as common practice.

Recent Posts

Deed signed to boost export link from new renewable energy zone to main demand centres

Work to start on sub-station and transmission line upgrades to boost the export capacity of…

14 July 2026

Australia’s biggest vanadium flow battery planned for clean energy precinct at former coal mine

A proposed 108 megawatt (MW), eight hour vanadium flow battery - with lower fire risk…

14 July 2026

Turbines and transmission towers up and concrete foundations poured at rare state-owned wind farm

State-owned wind farm marks a "huge few weeks of milestones" including delivery of transformers, erection…

13 July 2026

One of Australia’s biggest renewables developers seeks to build one of country’s biggest new gas plants

Plans for one of the nation's biggest new gas plants join the queue for federal…

13 July 2026

Regulator bans two solar and battery installers for failing to meet standards and regulations

Regulator says two individuals banned from installing solar PV and home batteries under the SRES…

13 July 2026

Andrew Forrest’s Squadron Energy unveils another big wind project near crowded renewable zone

Squadron's latest wind project located just outside of crowded renewable zone, and will seek to…

13 July 2026