Renewables

Neoen gets federal all-clear to build its first wind farm in Western Australia

Published by

Neoen Australia’s plans to build its first wind project in Western Australia have been waved through both state and federal environmental assessment processes, paving the way for its development in the same state where Neoen is building one of Australia’s biggest battery projects.

Neoen last year referred plans for the 200 megawatt (MW) Narrogin wind farm, including a 100 MW, 200 MWh battery component, to both the Western Australia Environment Protection Authority and the federal government’s Environment Protection & Biodiversity Conservation Act.

A decision was posted late last week on the EPBC portal determining that the proposed 25-turbine Neoen project is “not a controlled action” and therefore does not require full assessment and approvals under the federal Act.

The EPBC decision follows a similar decision from the WA EPA, posted in December 2024, not to fully assess the wind and battery proposal due to low levels of environmental and habitat disturbance, considering it is planned for predominantly agricultural land that has already been cleared.

Neoen’s Narrogin project has not had such a smooth run with the local government, however, with claims from Narrogin Shire Council that the developer has ignored a local planning policy that was set up to ensure new renewables projects are conducted in line with community wishes.

Narrogin has been struggling with the influx of renewable energy projects on its patch and, in 2023, put in place draft policies guiding how renewable energy should be implemented. 

In its environmental impact statement (EIS) for the project, Neoen claimed that the policy “would make most wind projects unviable while being very conservative and not evidence based.”

Neoen says it has been engaging with local stakeholders since 2022 and has promised to “go above and beyond” what the state requires when it comes to benefits sharing schemes. A community benefits fund attached to the wind farm will start at $225,000 a year.

Also in WA, Neoen is currently building the 560 MW, 2240 MWh Collie battery, and has already completed the first stage. It will be the biggest battery in the country when complete later this year, but will likely be overtaken by the Eraring battery in NSW, once the second and third stages of that project are complete in 2027.


If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Your support is invaluable.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s biggest energy users are being lined up to break the wind drought in its most coal dependent state

Data centres and the country's biggest aluminium smelter will finally get to break the long…

18 August 2026

The $2.5 billion wind project getting ready for take-off: But what about the crashed Cessna?

After more than two decades of planning, this huge wind project is edging closer to…

18 August 2026

One of Australia’s biggest wind projects seeks green light to add solar and battery

The developers behind a mammoth proposed 1.4 gigawatt (GW) wind farm is seeking federal environmental…

18 August 2026

What federal and state rebate changes mean for C&I solar and batteries – in 8 charts

Eight charts show how two big policy announcements in the space of a fortnight have…

18 August 2026

Safeguard will short-change climate targets, study says, rules should be tougher on fossil fuels

Australian investors are pushing for big changes to Australia's major pollution policy and they could…

18 August 2026

Bigger than Godzilla: Fortescue receives second shipment of turbine parts to top “self-lifting” towers

A second shipment of some of the biggest wind turbine parts yet seen in Australia,…

18 August 2026