Renewables

Bigger than Godzilla: Fortescue receives second shipment of turbine parts to top “self-lifting” towers

Published by

A second shipment of some of the biggest wind turbine parts yet seen in Australia, including the longest blades, has arrived in Port Hedland in Western Australia’s far north, en route to their Fortescue’s first wind farm in the Pilbara.

Fortescue has posted an update on the progress at its 133 megawatt (MW) Nullagine wind project, where the iron ore giant is testing a unique “self lifting” wind tower technology developed by Spain’s Nabrawind, now owned by Fortescue.

Topping the towers will be Envision’s technology, including 89 metre long blades, twice as long as a Boeing 737, according to Fortescue.

“With the second vessel now in port carrying the next set of parts, the operation is gathering pace,” Fortescue said in a post on LinkedIn on the weekend.

“We’re transporting these beasts 300 kilometres from Port Hedland to Nullagine, where we’re building a 133 MW wind farm to help power our operations with renewable energy.”

As Renew Economy has reported, Envision are also supplying the same 7.8 megawatt turbines – the most powerful to be deployed in Australia – to the Narrogin wind farm south of Perth, which began construction in July after project owner Neoen struck a long term offtake agreement with Synergy.

For Fortescue, the Nullagine wind project will be followed by a bigger wind project at the neighbouring Bonney Downs facility, along with 1.4 GW of solar that is currently being delivered elsewhere in the Pilbara.

The self lifting turbine tower technology allows for simpler and quicker erections, less concrete, and elevates the blades themselves to where there is generally more wind.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: Fortescue

Recent Posts

Data centres may be allowed to “build first, catch up later” on renewable mandate, AEMC’s Collyer says

Head of market rule maker says data centres may become "first load that is interruptible"…

12 October 2026

Two new big battery projects name contractors and suppliers as construction gets underway

Two new big battery energy storage systems under development in two states have taken important…

12 October 2026

Fresh delay to contentious Middle Arm gas project prompts call to “cancel it for good”

Middle Arm, a large gas and petrochemical hub earmarked for the NT and which green…

12 October 2026

“We’re building an army:” Angry anti-renewable groups take to city streets ahead of state election

A protest last week brought together a mishmash of causes but its core was opposition…

12 October 2026

Electrification can slash heavy industry bills and emissions – but new report says it will take a team effort

Government-subsidised power for major industries like smelters might not be needed if companies collaborated on…

12 October 2026

The High Court ruling on climate damage | Energy Insiders

Former EDO boss and now Greens MLC Sue Higginson on the huge implications of the…

12 October 2026