Battery

Neoen detaches big battery project from large wind farm development in central Queensland

Published by

Neoen has detached its Mount Hopeful battery from the wind project that surrounds it, and is now asking the regional council to approve it separately. 

The 350 megawatt wind project just outside Gladstone has all government approvals but is still in the final development phase, the developer says. 

Last week it asked the Rockhampton Regional Council to approve a standalone battery development, still with four hours of storage but slightly bigger at up to 600 megawatts (MW).

The battery has a proposed start year of 2028 for the first stage and will straddle Powerlink’s Bouldercombe to Larcom Creek 275 kilovolt (kV) power line reinforcement project. 

Neoen shifted the battery, a synchronous condenser, and transformers 500 metres to avoid federally protected environmental features, it said in a report sent to the Queensland State Assessment and Referral Agency (SARA).

What Neoen hasn’t revealed is why it’s detached the battery from the wind project, although planning delays at the broader Mount Hopeful project and for wind proposals generally could hold the answer.

Construction on the original Mount Hopeful wind and battery project was scheduled to start in the second half of 2023, but federal EPBC approval didn’t come through until a year later.

That approval came with a range of conditions to protect the southern and central greater glider, southern yellow-bellied glider, koala and northern quoll.

In the SARA documents dated April this year, Neoen said it expected to start work on both battery and wind sites this month with construction now taking 40 months instead of 22-28 months.

These kinds of delays are plaguing wind projects across the country, and it’s leading some  wind-focused developers shift to batteries and even solar-battery hybrids. 

Neoen is still focused on both, with 20 battery projects and 14 onshore wind projects in development, construction or commissioning today, according to RenewMap.

Mount Hopeful is its last remaining wind project yet to be developed in the sunshine state.

And given the Queensland government’s antipathy towards wind projects, separating contentious from uncontroversial technologies could be a sound strategy. 

The state government ment cancelled the $1 billion Moonlight Range project in May and effectively killed the 1.2 GW Forest Wind project in September, and has called in two other big projects.

Neoen may have some protection however, as it signed a 15-year power purchase agreement for the Mount Hopeful project with state-owned Stanwell Corporation in 2022. 

Stanwell will buy 65 per cent of the generation capacity from the project, or 215 MW.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

What fossil madness is this? Wars can’t interrupt flow of wind and the sun, but all we hear is drill, baby, drill

Australia is in the grip of a global fossil fuel crisis. It knows it has…

20 March 2026

Can Australia make its own wind turbine parts? Global giant suggests it might be at the whim of federal LNP

CEO of global wind giant says bipartisan agreement needed if local manufacturing is to be…

20 March 2026

Why some of Australia’s energy market conventions should go the way of the dinosaurs

We face some big challenges. To what extent should we protect businesses designed to operate…

20 March 2026

In the case of critical minerals, China did not take our lunch – we left it on the table

Australia needs to apply a new lens of green energy and industry statecraft, including developing…

20 March 2026

Energy Insiders Podcast: Why batteries are the answer to nearly everything

We talk to Jeff Monday from Fluence on the fall in battery costs and the…

20 March 2026

Independent panel approves gigawatt scale battery three months after local opponents force referral

Independent Planning Commission gives approval to gigawatt-scale standalone battery project just three months after it…

20 March 2026