Neoen gets federal all-clear to build its first wind farm in Western Australia

Published by

Neoen Australia’s plans to build its first wind project in Western Australia have been waved through both state and federal environmental assessment processes, paving the way for its development in the same state where Neoen is building one of Australia’s biggest battery projects.

Neoen last year referred plans for the 200 megawatt (MW) Narrogin wind farm, including a 100 MW, 200 MWh battery component, to both the Western Australia Environment Protection Authority and the federal government’s Environment Protection & Biodiversity Conservation Act.

A decision was posted late last week on the EPBC portal determining that the proposed 25-turbine Neoen project is “not a controlled action” and therefore does not require full assessment and approvals under the federal Act.

The EPBC decision follows a similar decision from the WA EPA, posted in December 2024, not to fully assess the wind and battery proposal due to low levels of environmental and habitat disturbance, considering it is planned for predominantly agricultural land that has already been cleared.

Neoen’s Narrogin project has not had such a smooth run with the local government, however, with claims from Narrogin Shire Council that the developer has ignored a local planning policy that was set up to ensure new renewables projects are conducted in line with community wishes.

Narrogin has been struggling with the influx of renewable energy projects on its patch and, in 2023, put in place draft policies guiding how renewable energy should be implemented. 

In its environmental impact statement (EIS) for the project, Neoen claimed that the policy “would make most wind projects unviable while being very conservative and not evidence based.”

Neoen says it has been engaging with local stakeholders since 2022 and has promised to “go above and beyond” what the state requires when it comes to benefits sharing schemes. A community benefits fund attached to the wind farm will start at $225,000 a year.

Also in WA, Neoen is currently building the 560 MW, 2240 MWh Collie battery, and has already completed the first stage. It will be the biggest battery in the country when complete later this year, but will likely be overtaken by the Eraring battery in NSW, once the second and third stages of that project are complete in 2027.


If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Your support is invaluable.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Researchers unlock new path for ultra low-cost solar by swapping out scarce and costly metal in PV cells

An international team of researchers has successfully built the first high-performance tandem solar cell that…

21 July 2026

Firefighter group hits back at “wild claims” and “fear mongering” over transmission lines and fire risk

"Wild claims" that fire fighters will not attend fires on properties hosting new transmission lines…

20 July 2026

Yes, we need more wind power. In the meantime, let’s get the most from the projects we have

Meeting our 82% renewables by 2030 target will take every lever available. Lifting the performance of…

20 July 2026

Should we send data centres into orbit: SpaceX, AI and the Emperor’s new clothes

Can or should data centres be sent into orbit? It might do away with land,…

20 July 2026

Network wars: Ausgrid demands lower transmissions fees as data centres gatecrash the grid

Australia's biggest DNSP is not happy that Transgrid is maxing out its network capacity, and…

20 July 2026

“Important milestone:” Finance landed for AC-coupled big battery to turn operating solar farm into hybrid

Danish renewables developer will add a two-hour big battery to an existing solar farm after…

20 July 2026