Hydrogen

Massive 6,000MW renewable hydrogen plans shelved over “water issues”

Published by

Plans for a potential six gigawatt-scale wind and solar backed renewable hydrogen production hub in South Australia have been shelved, the project’s developer has confirmed, due to “unacceptable” risks around water supply.

Kallis Energy Investments founder and executive chair, Terry Kallis, said in a statement on LinkedIn that the Moolawatana project – announced barely six months ago – was being discontinued based on the findings of an environmental assessment.

“That assessment, which was foreshadowed in the original project announcement, has determined that the environmental and permitting risks associated with water supply and desalination were unacceptable,” Kallis said.

“Hence, the project has been stopped.”

First unveiled in late November of 2021, the Moolawatana Renewable Hydrogen Project proposed the development of a green hydrogen hub near the Moolawatana Station around 570km north of Adelaide, backed by up 6,000MW of wind and solar generation.

The proposal, which was welcomed at the time by then SA energy minister Dan van Holst Pellekaan, was to include construction of a dedicated pipeline to facilities near Port Bonython, for processing green hydrogen into ammonia that could then be prepared for export.

Kallis has had previous involvement in the SA Starfish Hill wind farm and the Star of the South offshore wind farm currently under development in Victoria, and also led one of the many “hot rock” geothermal hopefuls that ultimately proved unsuccessful.

He is also still involved in the development of the proposed 5,000MW Murchison Renewable Hydrogen project in Western Australia.

The Murchison Hydrogen Renewables project proposed for near Kalbarri includes more than 5 gigawatts of wind and solar, a big battery, a 3GW electrolyser and the production of roughly 2 million tonnes a year of green ammonia.

A submission to the WA Environmental Protection Authority earlier this month detailed the scale and mix of technologies being proposed, and what it will take to get that similarly ambitious project up and running.

“Not all projects work and it is important that developers determine fatal flaws as early as possible in the project timeline and communicate this to stakeholders,” Kallis said of the Moolawatana project.

“The Moolawatana project is … unrelated to the WA Murchison project which is going full steam ahead – pardon the pun,” he added in comments below the LinkedIn post.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Huge wind and battery project becomes first to seal local benefits deal under rigorous new planning regime

Developer thanks council for helping navigate "evolving regulatory landscape" as it seals the first Community…

2 May 2026

“Let’s actually get projects up and running:” Report warns Australia’s green iron edge is at risk

Australia's renewable energy and rich iron ore deposits make it a potential leader in green…

1 May 2026

New changes trim “essential” REZ transmission route to avoid caves – and another 50 landholders

A new nip-and-tuck to plans for a major new REZ transmission line has trimmed it down…

1 May 2026

Energy Insiders Podcast: Electric trucks are profitable, but diesel struggles

Ben Hutt, the CEO of battery-swap electric truck company Janus Electric on the switch from…

1 May 2026

Claims of huge new blow-outs to the Snowy 2.0 bill are just plain wrong

The latest, much-inflated price estimates Snowy 2.0 critics have come up with for the pumped…

1 May 2026

Cost of poles and wires jumps sharply, but regulator says cost to consumer still likely to fall

Households could see a modest reduction in the cost of poles and wires in their…

1 May 2026