Genex Power Limited (ASX: GNX) (Genex or Company) is pleased to provide shareholders with this latest update regarding the construction program for the Company’s Phase One 50MW Kidston Solar Project (KSP1 or Project).

Genex advises that the construction of KSP1 continues to remain on time and on budget for first generation in Q4 2017 and Practical Completion in Q1 2018. Key activities since the last update (refer ASX announcement 20 April 2017) include:

  •   First delivery of First Solar Thin-Film solar modules complete;
  •   First delivery of NEXTracker components underway;
  •   Piling rigs mobilized to site ahead of pile delivery;
  •   Ergon switchyard equipment 75% installed and equipment earthing underway;
  •   Solar farm substation earth-grid installed;
  •   Laydown area for materials storage and component assembly 100% complete; and
  •   Site clearing approximately 90% complete.
Solar panels stored on laydown area.
Solar panels stored on laydown area.

Commenting on the recent progress of KSP1, Managing Director of Genex Power Michael Addison said, “Genex’s focus on project delivery continues with the project continuing to perform to budget. Kidston is now a hive of activity with 65 people employed on site. The outlook for wholesale electricity and Large-scale Generation Certificates (LGCs) remains robust which underpins the potential to deliver strong cash flows to Genex”.

The Federal Government, through the Australian Renewable Energy Agency has provided $8.9 million funding to support the construction of the $126 million Project at Genex’s Kidston Solar Farm.


CONTACT:

Simon Kidston

Executive Director
Tel: +61 2 9048 8852
Email: sk@genexpower.com.au

Share
Published by

Recent Posts

Chickens “coming home to roost” for next Victorian energy minister, whoever it might be

The coming three years will be exceptionally tough for Victoria's next energy minister, experts say.

28 October 2026

World’s biggest battery maker snags deal for new Australian project, sees “huge interest” in sodium tech

China battery giant reveals it has been selected as the tech partner for a major…

28 October 2026

Victoria Coalition promises quick review of transmission plans, as it soft pedals stance on renewables

Victoria's likely next energy minister seeks to woo clean energy summit, promising quick fire review…

28 October 2026

Andrew Forrest’s Fortescue signs first 3rd party supply deal for its giant Pilbara “green grid”

Andrew Forrest's Fortescue signs up owner of huge lithium mine as the first customer of…

28 October 2026

Wind and solar projects to be given revenue certainty in new market design to back 75 pct renewables target

Updated: A simplied version of the new national policy mechanism will be used to propel…

28 October 2026

WA wants more renewables, but that does not mean it needs more gas

W.A. should easily meet its 75 pct renewables target, but there is a big question…

28 October 2026