Construction progress

Following Financial Close of the Phase One 50MW Kidston Solar Project (KSP1 or Project), Genex Power Limited (ASX: GNX) (Genex or Company) is pleased to advise that the construction program is well underway and remains on track. Key activities include:

  • Site clearing commenced
  • Detailed design 30% complete
  • Construction camp operational with accommodation available for 84 personnel
  • Kidston substation civil works 50% complete and on track for completion and handover toErgon in April 2017
  • Orders placed for major components including solar panel modules, tracking systemframes and inverters
Figure 1: Construction works at the Kidston Substation
Figure 1: Construction works at the Kidston Substation

 

Figure 2: Site clearing commenced
Figure 2: Site clearing commenced

The Project remains on budget and on track for First Generation in Q4 2017 and Practical Completion in Q1 2018.

Project revenue and EBITDA outlook

The Australian wholesale electricity market continues to be impacted by escalating domestic gas prices and a changing generation mix, including intermittent renewable generation. Many industry participants anticipate more volatility and higher energy prices going forward.

Against this background, Genex recently conducted an extensive “back-test” modelling exercise to determine potential Project revenues and EBITDA.

The “back-test” model was based on actual historical half-hourly wholesale electricity prices in the National Electricity Market (NEM) over the course of the past 3 years and on the assumption that the Project had operated at its design capacity of approximately 145,000MWh over the course of the modelling timeframe.

Based on historical NEM pricing data, and on the assumption that the Project had been in operation over the full 36 month period to 28 February 2017, the following annual Project revenues and Project EBITDA figures would have been achieved:

Results are theoretical and based on anticipated generation and actual historical half-hour pricing data over the modelling period. These results are in no way an indication of future performance of the Project. EBITDA is at the Project level, and therefore before corporate overheads.

12 months ended 28 Feb 2017

12 months ended 29 Feb 2016

12 months ended 28 Feb 2015

Revenue

$16.8m

$13.8m

$14.1m

EBITDA

$15.2m

$12.2m

$12.5m

 

ASX Announcement

15 March 2017

The development of low cost, efficient energy storage, using mature technology, remains the key focus for Genex. Genex remains focused on developing its Kidston Renewable Energy Hub, comprising a 250MW Pumped Storage Hydro Project and a co-located 270MW Solar Project (Phase Two). Genex is engaging with a number of key stakeholders in relation to the funding of its Energy Hub.

Commenting, Managing Director of Genex Power Michael Addison said, “The theoretical financial performance of the 50MW Kidston Solar Project (assuming it had been in operation historically) has the potential to provide a solid revenue and earnings platform for Genex, going forward. Genex remains focused on continuing the development of its Kidston Renewable Energy Hub initiative in the soonest possible time”.


CONTACT:

Michael Addison

Managing Director
Tel: +61 2 9993 4411
Email: ma@genexpower.com.au

About Genex Power Limited:

Simon Kidston

Executive Director
Tel: +61 2 9993 4443
Email: sk@genexpower.com.au

Genex Power is a power generation development company listed on the ASX. The Company is focused on innovative clean energy generation and electricity storage solutions which deliver attractive commercial returns for shareholders. Following Financial Close of Kidston Solar Stage 1 (50MW) Project, the Company’s focus will now move onto the development of its 250MW Kidston Pumped Storage Hydro Project and the Kidston Solar Project Phase Two 270MW located at the Kidston Renewable Energy Hub, in Northern Queensland.

Share
Published by

Recent Posts

“Grand Theft Antalya:” A climate heist, or should we stop expecting COPs to call time on fossil fuels?

A global compact on phasing out fossil fuels seems increasingly unlikely as COP31 crawls to…

20 November 2026

Energy Insiders Podcast: On the ground at COP31

IGCC's Anna Hancock offers on-the-ground insight into what has – and hasn't – been happening…

20 November 2026

“100 towers raised:” State ticks off major transmission milestones, kicks off helicopter wire stringing

State's build-out of major new transmission projects hits important milestones, including 100 transmission towers in…

20 November 2026

Fire service thanks wind farm workers for “quick action” on neighbouring hay shed fire

Country Fire Service praises the "quick action" of 20 wind farm workers from an un-named…

20 November 2026

State orders rooftop solar switch-off, asks for patience, as wild storm cuts power to 24,000 properties

Around 24,000 South properties have been cut off from power – and rooftop solar switched…

20 November 2026

Big batteries to boost reliability over summer, says AEMO, as extreme weather meets changing demand

More than 6 GW of added big battery capacity will help Australia's electricity grids rise…

20 November 2026