Kidston solar project update

Published by

PRESS RELEASE

Construction progress

Following Financial Close of the Phase One 50MW Kidston Solar Project (KSP1 or Project), Genex Power Limited (ASX: GNX) (Genex or Company) is pleased to advise that the construction program is well underway and remains on track. Key activities include:

  • Site clearing commenced
  • Detailed design 30% complete
  • Construction camp operational with accommodation available for 84 personnel
  • Kidston substation civil works 50% complete and on track for completion and handover toErgon in April 2017
  • Orders placed for major components including solar panel modules, tracking systemframes and inverters
Figure 1: Construction works at the Kidston Substation
Figure 1: Construction works at the Kidston Substation

 

Figure 2: Site clearing commenced
Figure 2: Site clearing commenced

The Project remains on budget and on track for First Generation in Q4 2017 and Practical Completion in Q1 2018.

Project revenue and EBITDA outlook

The Australian wholesale electricity market continues to be impacted by escalating domestic gas prices and a changing generation mix, including intermittent renewable generation. Many industry participants anticipate more volatility and higher energy prices going forward.

Against this background, Genex recently conducted an extensive “back-test” modelling exercise to determine potential Project revenues and EBITDA.

The “back-test” model was based on actual historical half-hourly wholesale electricity prices in the National Electricity Market (NEM) over the course of the past 3 years and on the assumption that the Project had operated at its design capacity of approximately 145,000MWh over the course of the modelling timeframe.

Based on historical NEM pricing data, and on the assumption that the Project had been in operation over the full 36 month period to 28 February 2017, the following annual Project revenues and Project EBITDA figures would have been achieved:

Results are theoretical and based on anticipated generation and actual historical half-hour pricing data over the modelling period. These results are in no way an indication of future performance of the Project. EBITDA is at the Project level, and therefore before corporate overheads.

12 months ended 28 Feb 2017

12 months ended 29 Feb 2016

12 months ended 28 Feb 2015

Revenue

$16.8m

$13.8m

$14.1m

EBITDA

$15.2m

$12.2m

$12.5m

 

ASX Announcement

15 March 2017

The development of low cost, efficient energy storage, using mature technology, remains the key focus for Genex. Genex remains focused on developing its Kidston Renewable Energy Hub, comprising a 250MW Pumped Storage Hydro Project and a co-located 270MW Solar Project (Phase Two). Genex is engaging with a number of key stakeholders in relation to the funding of its Energy Hub.

Commenting, Managing Director of Genex Power Michael Addison said, “The theoretical financial performance of the 50MW Kidston Solar Project (assuming it had been in operation historically) has the potential to provide a solid revenue and earnings platform for Genex, going forward. Genex remains focused on continuing the development of its Kidston Renewable Energy Hub initiative in the soonest possible time”.


CONTACT:

Michael Addison

Managing Director
Tel: +61 2 9993 4411
Email: ma@genexpower.com.au

About Genex Power Limited:

Simon Kidston

Executive Director
Tel: +61 2 9993 4443
Email: sk@genexpower.com.au

Genex Power is a power generation development company listed on the ASX. The Company is focused on innovative clean energy generation and electricity storage solutions which deliver attractive commercial returns for shareholders. Following Financial Close of Kidston Solar Stage 1 (50MW) Project, the Company’s focus will now move onto the development of its 250MW Kidston Pumped Storage Hydro Project and the Kidston Solar Project Phase Two 270MW located at the Kidston Renewable Energy Hub, in Northern Queensland.

Share
Published by

Recent Posts

Fast lane to electric, and Snowy blowouts | Energy Insiders

Bruce Hardy from the Energy Futures Foundation on the fast track to electric transport, and…

29 October 2026

WA renewable energy target sends investors the signal they need – at a critical time

A strong state target for renewables sends the message that WA is a stable market.…

29 October 2026

Ratings system designed to restore trust in wind and solar developers goes live, with first batch scoring well

Online rating tool that ranks renewable energy developers and transmission companies against seven key criteria,…

29 October 2026

“Anti-renewables populism is the largest unpriced risk:” But poll data shows support is growing, even in hot zones

Polling by Squadron Energy finds higher support than expected in western Victoria and central NSW,…

29 October 2026

LNP hits brakes on pumped hydro project, spooked by Snowy 2.0 cost blowout

Contracting for huge pumped hydro project has reportedly been suspended by the state treasurer and…

29 October 2026

Snowy 2.0: The potentially $50 billion shambles that really needs a proper cost-benefit analysis

Even now, with $12 billion sunk, stopping Snowy 2.0 may be the least-worst decision. It…

29 October 2026