Huge six-hour battery gets federal green tick for grid sweet-spot at edge of coal hub

Published by

Plans to install a big battery with up to six hours of energy storage capacity in a sweet spot between Victoria’s coal generation heartland and Melbourne’s major electricity demand areas have been waved through the federal green queue.

The up to 400 megawatt (MW) and 2,400 megawatt-hour (MWh) Bunyip North Battery Energy Storage System (BESS) was this week determined not to require further assessment through the federal government’s environmental assessment process, the EPBC Act.

Res, the renewables developer behind the project, has welcomed the decision – which comes almost exactly one month after the project was referred for assessment – and says the project will now continue to progress through the relevant state and local planning processes.

When the project was referred to the EPBC, Res said the location for the battery was chosen to avoid other places that have sensitive environmental claims, or that were close to homes. 

“Extensive environmental studies have confirmed the project is unlikely to have a significant impact on nationally protected species or habitats, and that gives us confidence as the project progresses through the assessment process,” Res director Greg Wilkinson said at the time. 

In a statement issued this week, Res said that the federal environment minister’s determination that the battery did not need to undergo the full assessment process, confirmed is was “not expected to have a significant impact on matters of national environmental significance.”

The Bunyip North BESS is proposed for construction around 3km from Bunyip, in Gippsland, on the traditional lands of the Bunurong People.

Res says the site is mostly rural land, currently used for grazing and cropping, and was also picked for its strategic location between the Latrobe Valley – the coal generation centre of Victoria – and Melbourne, and next to existing transmission lines and a major highway.

The transmission lines are the same that deliver power from Victoria’s remaining Latrobe Valley coal power stations to Melbourne – and, one day, will transport electricity generated by the offshore wind farms being developed off the coast of Gippsland.

“The Project Area also benefits from good access to transport infrastructure, being located adjacent to Princes Freeway.” The BESS will connect to the existing network via a new transmission terminal station, the Bunyip North Terminal Station.

“Following the outcomes of environmental surveys … the Project Area was selected to avoid direct impacts to Matters of National Environmental Significance (MNES) whilst remaining in proximity to existing transmission infrastructure,” the EPBC referral documents say.

The referral documents also note that, at the end of its operational life, the BESS may be upgraded, repowered, or decommissioned subject to relevant land agreement and planning approval requirements.

“Decommissioning activities will be conducted in accordance with applicable approvals and regulatory requirements and will generally include the removal of above-ground infrastructure and services, and rehabilitation of the site to a stable condition consistent with surrounding land uses.

“The BNTS may remain in place for ongoing use as part of the transmission network as operated by the Declared Transmission System Operator.”

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s biggest energy users are being lined up to break the wind drought in its most coal dependent state

Data centres and the country's biggest aluminium smelter will finally get to break the long…

18 August 2026

The $2.5 billion wind project getting ready for take-off, 23 years after farmer landholders were first approached

After more than two decades of planning, this huge wind project is edging closer to…

18 August 2026

One of Australia’s biggest wind projects seeks green light to add solar and battery

The developers behind a mammoth proposed 1.4 gigawatt (GW) wind farm is seeking federal environmental…

18 August 2026

What federal and state rebate changes mean for C&I solar and batteries – in 8 charts

Eight charts show how two big policy announcements in the space of a fortnight have…

18 August 2026

Safeguard will short-change climate targets, study says, rules should be tougher on fossil fuels

Australian investors are pushing for big changes to Australia's major pollution policy and they could…

18 August 2026

Bigger than Godzilla: Fortescue receives second shipment of turbine parts to top “self-lifting” towers

A second shipment of some of the biggest wind turbine parts yet seen in Australia,…

18 August 2026