Glenrowan West solar farm completes commissioning in Victoria

Published by

The Glenrowan West solar farm between Benalla and Wangaratta in Victoria has been completed and declared fully operational, complete with a “sizeable” flock of sheep.

Project manager Wirsol Australia said on Thursday that construction and commissioning of the 149MW (110MW AC) solar farm had been completed and it was now ready to supply about 265GWh of renewable energy a year, enough to power 41,000 households.

“With construction finished, the site has also become home to a sizeable flock of sheep, which are there to help manage the vegetation whilst fulfilling their previous agricultural roles for local farmers,” Wirsol said in an a statement.

Photo: Wirsol

“The use of sheep to maintain vegetation mean that significantly less mowing and spraying is required, thus reducing both carbon emissions and herbicide use, while allowing land management to occur in a sustainable manner.

“This forms part of WIRSOL’s ongoing commitment to sustainable agri-solar practices which are being implemented on several solar farms within our portfolio and provide an ideal outcome for the power plant, local farmers and the environment as a whole.”

Glenrowan West solar farm. Image: Wirsol.

The project is owned by German-based solar developer Wirtgen Invest, which acquired the project in January, marking the company’s first move into the Australian renewables market.

The project’s EPC contractor was the wholly-owned Australian subsidiary of US-based Signal Energy, appointed in February.

See also RenewEconomy’s Large Scale Solar Farm Map of Australia

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024