The 130MW Glenrowan solar farm in Victoria is now fully commissioned, with construction through to going live taking just 12 months.
The news was announced in a LinkedIn post by UGL renewable energy connections manager James Brennan, who said hold point testing was complete and the solar farm is now operating at “full unconstrained capacity.”
“Another very successful EPC project by UGL New Energy, also being the 3rd major utility scale solar project completing commissioning by our team within just 12 months!” Brennan wrote.
Cimic Group company Pacific Partnerships energised the Glenrowan Solar Farm in late November last year and began exporting electricity to the national grid in December. It is still waiting on AEMO’s final approval before officially launching.
It planned to ramp up to full production by the end of March 2024, to supply some 45,000 homes.
Located on 245 hectares in Victoria’s proposed North East Renewable Energy Zone (REZ), the solar farm has grid connection and service agreements with the Victorian transmission network operator AusNet and the Australian Energy Market Operator (AEMO).
The Glenrowan Solar Farm is contracted through a 10-year power purchase agreement with the Victorian Government.
Just five days ago UGL said it was “steadily making strides towards completion in early 2024” and noted the volume of work completed in the last 12 months, including 32,000 piles laid for 226,000 solar panels, and 2,150 trackers.
AEMO reports record number of newly commissioned projects in last fiscal year, but wind and…
The increase in data centre demand is being overshadowed by the much larger increase in…
AEMC commissioner Rainer Korte on what the new rules on reporting and data sharing will…
Developer says it is good to go on early works and construction of the largest…
AEMO says proof that grid forming battery inverters can deliver heartbeat of the grid will…
Days after lodging new plans for a more than 500 MW wind farm, Squadron dumps…