A flurry of new solar and battery projects have appeared in the energy market operator’s grid management system in the past two weeks, driving home just how popular the two technologies have been with investors, both separately and together as solar-battery hybrids.

The first to appear, last week, was Acen Australia’s 200 megawatt (MW), 400 megawatt-hour New England battery energy storage system (BESS), which has been installed next to what remains one of the biggest PV projects in the country, the 720MW New England solar farm.

As Renew Economy has reported, the New England BESS was backed by the NSW government’s Emerging Energy Program, a $75 million initiative to fast-track the development of new firmed renewables, as the state prepares for a grid beyond coal.

The solar component – the first 400 MW stage of which was completed by the start of last year – is also backed by a 20 year underwriting agreement from the NSW state government.

As Global Power Energy’s Geoff Eldridge explains here, the New England BESS is listed on AEMO’s Market Management System (MMS) as two bidirectional battery units, under two different Dispatchable Unit Identifiers (DUIDs).

“The New England BESS split across two DUIDs is … a useful reminder that larger BESS projects can appear in MMS as multiple unit groupings rather than a single line item,” Eldridge says.

Also joining the AEMO dashboard towards the end of last week were two solar farms – Global Power Generation’s 100 MW Bundaberg Solar Farm, in Queensland and European Energy’s 80 MW Lancaster Solar Farm in Victoria.

Interestingly, both of these projects are backed by power purchase agreements with high profile corporate customers: Tesltra for the Bundaberg project and Apple for Lancaster. Accordingly, notes Eldridge, both projects are listed with AEMO as semi-scheduled generating units.

And while it’s solar and batteries coming into the grid management system this month, it’s new wind projects that have this week dominated new projects to join the federal EPBC queue, perhaps lending weight to the idea that 2026 might be a comeback year for wind power.

New to the queue for federal environmental assessment this week is the Twin Hills wind farm, an up to 110 turbine project and battery being proposed by Wind Prospect for 30 km north-east of Eneabba and 260 km north of Perth in Western Australia.

Also there is a proposal from Equis Wind Australia to build a 600 MW wind farm and “associated ancillary infrastructure” in Jackson North, around 35 km south-west of Wandoan in Queensland.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026