Genex kicks off works on Kidston pumped hydro, next to solar farm

Published by

Work is set to begin on the pumped hydro storage component of Genex Power’s ground-breaking Renewable Energy Hub at Kidston, in North Queensland, as the company works to keep the massive project moving while it awaits financial close.

Genex said on Friday that it had entered into an agreement with McConnell Dowell and John Holland, to immediately commence an early works program on the 250MW K2-project, which will supply up to eight hours storage, using the existing pits of a former gold mine.

Under the agreement, the MDJH joint venture will start work on an agreed program of works to accelerate the development of the pumped hydro project, ahead of financial close, which is said to be on track for the first half of 2019.

In June last year, the Kidston project was granted $516 million in concessional finance from the federal government’s Northern Australia Infrastructure Facility (NAIF), to account for the bulk of the project debt funding.

At the time, Genex executive director Simon Kidston said the NAIF facility would be ranked as “subordinated debt”, meaning that any other bankers brought on board would get priority if things went awry – a key point in negotiating the cost of finance, as Giles Parkinson pointed out.

Then, in December, Genex signed a deal with EnergyAustralia giving exclusive rights to the utility to negotiate an off-take agreement for Kidston’s output, including an option to buy a half share in the storage component.

And while that agreement stopped short of inking a PPA, it was still hailed as a significant milestone for the project and a precursor to locking in finance in the first half of 2019.

The agreement this week will get things moving on the time-consuming and complex job of hydraulic design of the hydro turbines, followed by preliminary electrical design work and other project preparation activities, Genex said.

The ground-breaking Kidston Renewable Energy Hub – which all up aims to combine 320MW of solar PV, 250MW of pumped hydro, and possibly even 150MW of wind capacity – is hoping to achieve the renewables “holy grail” of 24/7 dispatchable power.

The first 50MW solar farm has been built, and Genex is now working on adding another 270MW of solar, as well as the pumped hydro energy storage system, which will use the existing pits of a former gold mine to provide 10 hours of storage.

“Embarking on this early works program with the MDJH-JV is a significant milestone for Genex as work gets underway on our biggest project which has been in planning for a number of years,” said Genex CEO James Harding in comments on Friday.

“Genex continues to work closely with Powerlink, the Queensland State Government, NAIF, ARENA, EnergyAustralia and other key stakeholders to finalise the remaining activities ahead of the Financial Close milestone,” Harding said.

“The Kidston Pumped Hydro Project will play a vital role in facilitating and supporting the further penetration of renewable energy in the National Electricity Market.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Networks brace for solar eclipse that threatens to cut power generation by 9.7 GW

Transmission system operators across Europe are bracing for the total solar eclipse that will sweep…

12 August 2026

Licences sought for Australia’s biggest wind, solar and battery hybrid to power giant gold mines

Licences sought for the biggest wind, solar and battery hybrid of its type, supplying 70…

11 August 2026

Pakistan’s citizen-led solar rush: Where panels power education and health – and are gifted in dowries

In Pakistan, a country with 250 million people and a GDP per capita of about…

11 August 2026

Plans for one of Australia’s biggest new gas plants sail through EPBC queue in just over two weeks

As wind generation proposals get stuck in EPBC limbo, plans for what could be the…

11 August 2026

Last turbine goes up as major wind farm completes expansion to become biggest in state

The last of 30 additional turbines have been added to existing wind farm, making it…

11 August 2026

Investor behind Amber Electric hits $10 million under management, milestone for new fund

Sydney based early-stage climate technology investor reaches $10 million under management and secures first close…

11 August 2026