Final turbine installed at one of Australia’s largest and lowest cost wind farms

Published by

The final turbine has been installed at the second stage of the Murra Warra wind farm in Victoria, completing a lengthy construction process for what will be one of the country’s biggest wind projects.

The  440MW Murra Warra project – now fully owned by Partners Group and located near Horsham in western Victoria – has had one of the more interesting construction and connection histories in Australia’s main grid.

It started off in 2017 with a long term off take agreement with Telstra for the 231MW first stage, for what was described at the time as a “stunning low cost” for wind energy, but problems emerged when its wind turbine supplier Senvion collapsed, before being sold to Siemens Gamesa.

For the 208MW second stage, which has a long term contract with the government owned Snowy Hydro, the developers turned to GE and its 5.5MW Cypress 5.5-158 turbines which were, at least for a short while, the biggest to be installed in Australia.

The second stage of the wind project also includes a synchronous condenser, required under the former “do no harm” rules that have now been ditched.

It is currently half way through the commissioning process for the second stage of the project, with 13 of the 38 turbines now generating and expectations of being in full production within three months.

The final turbine installed at Murra Warra wind farm. Source: Murra Warra twitter account.

RES, the original developer which retains construction and management rights over the project, said in a statement on Monday that it has completed construction with the erection of the final turbine of Stage II of the 99 turbine, 440MW facility..

It noted construction on the first stage started in 2018, and on the second stage in 2020, generating more than $100 million in economic benefits over the life of the project in jobs and local spend.

“The team rose to the challenge of constructing a wind farm through the pandemic and global supply shortages and it is a credit to them that construction has been completed within target timeframes,” RES head of  construction management Anthony Berzi said.

RES describes itself as the world’s largest independent renewable energy company, with more than 9GW of operational wind, solar and storage assets globally, and more than 3GW of wind and solar in Australia.  It has offices in Sydney, Melbourne, Brisbane and multiple regional locations.

RES is engaged in all technologies: wind, solar and storage and offer development plus construction and asset management services across Australia. To date, RES has managed a portfolio of 3GW of wind and solar assets in Australia.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Bowen launches review of emission caps and credits for Australia’s biggest carbon polluters

Policy review will investigate settings for Australia's 2030 and 2035 emissions reduction targets.

7 August 2026

Energy Insiders Podcast: Will data centres make or break wind?

Kane Thornton has moved from the peak renewables body to data centres, now the presumed…

7 August 2026

Climate Active is dead. The funeral will not be certified carbon neutral

Australia's government-run "carbon neutral" certification scheme is being wound up. It is good news for…

7 August 2026

Australia’s first offshore wind auction is “going ahead as planned,” new energy minister confirms

Victoria's newly appointed energy minister says the state will go ahead as planned with Australia's…

7 August 2026

Labor’s data centre gas double-speak leaves the gate open for dodgy offsets

A promise of banning gas while waving through “gas firming” and “gas peaking” with unlimited offsets leaves…

7 August 2026

Massive wind project, with up to 280 of Australia’s biggest-ever turbines, seeks federal green tick

Plans for a potentially massive new wind farm start federal environmental assessment, proposing up to…

7 August 2026