Renewables

Turbine shut downs at Victoria wind farm part of “staged maintenance,” says Squadron

Published by

Squadron Energy has confirmed that a number of turbines at the 226 megawatt (MW) Murra Warra 1 wind farm in north-western Victoria are temporarily out of action, as part of “staged maintenance” to replace failed bearings.

A spokesperson for Squadron said on Wednesday that work on a bearing refurbishment program on around half of the turbines at Murra Warra started recently and is expected to be completed next year.

Squadron says the works are limited to 32 of the project’s 61 Senvion turbines, with 15 currently switched off to undergo maintenance – half of the number claimed in local media reports on Wednesday.

“The wind farm continues to generate power, with staged maintenance taking place to replace certain failed bearings, and a number of turbines have already returned to service,” the spokesperson said in an emailed statement.

“Wind turbines are operational for 30 years or longer. As with a car or any other large complex machine, there is ongoing maintenance and some parts may warrant refurbishment.”

The Murra Warra wind farm – which totals 429 MW with the addition of the 209 MW stage 2 project – is a significant project for Victoria, delivering electricity under long-term contracts to Telstra, and a consortium of customers that includes ANZ, Coca Cola Amatil and the University of Melbourne, as well as Monash University.

Stage one of the Murra Warra project north of Horsham first started exporting electricity to the grid in early 2019, when it was under the ownership of Macquarie Group and renewable energy developer RES Australia.

Murra Warra 1 and 2 were acquired by Squadron Energy as part of the CWP Renewables sale by Partners Group.

The wind turbines for Murra Warra 1 were supplied by the now defunct German wind turbine manufacturer Senvion, which had put itself into administration by the time Murra Warra 1 started powering up.

By the end of 2019, Senvion had sold its European service fleet to Siemens Gamesa. Only the Indian division of the company – Senvion India – remains, after it was acquired by Saudi Arabian company, Alfanar, in 2021.

  • In the case of the Murra Warra turbines, the German manufactured bearings are being transported to Melbourne for refurbishment at a specialised facility.

Squadron says the maintenance works do not affect any of the turbines at Murra Warra 2.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australian company behind home battery that Bowen bought enters administration, hit by flood of “cheaper” imports

Australian battery maker whose customers include the federal energy minister has gone into voluntary administration,…

2 October 2026

Environmental approvals process kicks off for giant transmission line Coalition has vowed to scrap

A major new transmission line that the state opposition has vowed to scrap is seeking…

2 October 2026

Cannon-Brookes’ Atlassian signs deal with groundbreaking community solar farm to power its new green HQ

One of Australia's largest technology companies has signed a decade-long deal with a community-owned solar…

2 October 2026

“Deeply disappointing:” State blocks gas connection rule made to protect consumers from death spiral

South Australia decides not to make consumers pay for gas installations up front, delaying the…

2 October 2026

Large wind farm and big battery approved, subject to road rules and threatened bird management plan

Big wind and battery project approved by independent panel, subject to conditions, after state planning…

2 October 2026

Origin Energy drops plan for massive wind project in New England, citing rising costs

Origin Energy has dropped plans to develop a major wind farm intended for 10 kms…

1 October 2026