PRESS RELEASE
The substation and transmission line to link to the Cattle Hill Wind Farm to the transmission network has been completed and energised by TasNetworks.
Goldwind Australia Managing Director, John Titchen, said the substation’s completion is a major milestone for the project.
“Goldwind is pleased to be partnering with TasNetworks to achieve successful energisation of the substation for the Cattle Hill Wind Farm project. We have found the TasNetworks team to be very professional and capable.” said John.
“The commissioning and energisation of the substation is a key milestone in the project and has been made possible through a great team effort from everyone involved.” said TasNetworks CEO, Lance Balcombe.
“In addition to the construction of the substation on the wind farm site, approximately 130 metres of new transmission line has been built to connect the project to the existing transmission network and approximately three kilometres of existing transmission lines has been reconfigured to accommodate the future power output from the project.
“Construction of the project is progressing on many work fronts, six Goldwind turbines have now been installed and commissioning of turbines will commence shortly.
“Goldwind and Power China Resources Group appreciate the significant project progress, reflecting a team effort by many major project partners and approximately 150 staff currently working on site. Construction of the wind farm is planned for completion by the end of 2019” commented John.
Once the turbines are commissioned and generating power later this year, power will be fed via transmission line to the Waddamana substation and then into the state-wide transmission network. Once operational, Cattle Hill Wind Farm will produce enough clean energy to power approximately 63,500 Tasmanian homes.
Developer thanks council for helping navigate "evolving regulatory landscape" as it seals the first Community…
Australia's renewable energy and rich iron ore deposits make it a potential leader in green…
A new nip-and-tuck to plans for a major new REZ transmission line has trimmed it down…
Ben Hutt, the CEO of battery-swap electric truck company Janus Electric on the switch from…
The latest, much-inflated price estimates Snowy 2.0 critics have come up with for the pumped…
Households could see a modest reduction in the cost of poles and wires in their…