Press Releases

Cattle Hill Wind Farm substation energised

Published by

PRESS RELEASE

The substation and transmission line to link to the Cattle Hill Wind Farm to the transmission network has been completed and energised by TasNetworks.

Goldwind Australia Managing Director, John Titchen, said the substation’s completion is a major milestone for the project.

“Goldwind is pleased to be partnering with TasNetworks to achieve successful energisation of the substation for the Cattle Hill Wind Farm project. We have found the TasNetworks team to be very professional and capable.” said John.

“The commissioning and energisation of the substation is a key milestone in the project and has been made possible through a great team effort from everyone involved.” said TasNetworks CEO, Lance Balcombe.

“In addition to the construction of the substation on the wind farm site, approximately 130 metres of new transmission line has been built to connect the project to the existing transmission network and approximately three kilometres of existing transmission lines has been reconfigured to accommodate the future power output from the project.

“Construction of the project is progressing on many work fronts, six Goldwind turbines have now been installed and commissioning of turbines will commence shortly.

“Goldwind and Power China Resources Group appreciate the significant project progress, reflecting a team effort by many major project partners and approximately 150 staff currently working on site. Construction of the wind farm is planned for completion by the end of 2019” commented John.

Once the turbines are commissioned and generating power later this year, power will be fed via transmission line to the Waddamana substation and then into the state-wide transmission network. Once operational, Cattle Hill Wind Farm will produce enough clean energy to power approximately 63,500 Tasmanian homes.

Share
Published by

Recent Posts

Huge landowner-led wind project seeks green tick, despite looming threat to transmission link

A landowner-led wind farm is seeking state and federal environmental approvals, but could struggle to…

22 September 2026

“Like spinning 42 plates in the air at the same time:” How this impossible project broke Australia’s wind drought

The biggest wind project to begin construction in Australia this past year faced multiple hurdles.…

22 September 2026

Biggest coal project lines up for approval as Albanese calls for “bravery” in climate action

As the PM calls for climate "bravery" at a global summit in New York, NSW…

22 September 2026

“More cheap, clean sovereign energy:” Bowen and market operator celebrate new renewables record

Bowen and AEMO celebrate new renewables record - first time above 80 pct in main…

22 September 2026

Victorian Labor toes federal line on BYO renewables for data centres, Coalition still pushing gas

Victorian Labor says it will adopt the proposed federal Labor mandate and require future data…

22 September 2026

Global wind giant expects lower costs from new turbine equipped with extra-long blades

Powerful new wind turbine adds longer blades to reduce costs and boost output, and comes…

22 September 2026