Brigalow, the little solar farm that could, sending power to grid in Queensland

Published by

The 35MW Brigalow Solar Farm in Yarranlea, near Pittsworth, in Queensland has begun sending power to the grid.

The solar farm, which is owned by the solar arm of the Impact Investment Group, has had a rocky road to generation, marked by a legal battle with the Queensland government and a brush with fire in September of last year.

The legal battle came about when the managers of Brigalow – Maryborough Solar – filed a claim in the Queensland Supreme Court arguing that a state-government led rule change affecting solar installations would add around $2.6 million to the cost of the Yarranlea project, which at that time was already under construction.

The rule change, which was for a short period of time brought into effect in the state last year, required licensed electricians to mount and fix solar panels on PV projects of 100kW and larger – a job that had been performed by unskilled labourers and trades assistants.

Industry fought the rule from its inception, arguing that the new safety measure was a “ridiculous” overreach, and that it would cost jobs and blow out the costs and schedules of projects already under development. For projects in the planning stages, it threatened to rule them out completely, they said.

But it was the Brigalow solar farm that won the day. As we reported at the time, the Supreme Court found in Maryrorough Solar’s favour, and declared the government’s rule change “invalid” – a decision that was upheld up in a subsequent appeal – forcing the minister for industrial relations back to the negotiating table.

Welcome to the grid, Brigalow. More power to you! Credit for the chart, as always, goes to Paul McArdle from Global Roam, the providers of our popular NEM-Watch widget.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s biggest solar-battery hybrid project secures grid connection approval

Grid connection approval has been secured for massive solar farm and eight-hour battery hybrid project,…

8 June 2026

Bowen urged to “lead with vision and ambition” as he takes helm of Bonn climate talks

Bowen urged “to lead with vision and ambition" as he heads to Bonn to take…

8 June 2026

Solar projects to be hit by big increase in costs due to new Australian anti-dumping decision

Utility solar projects in Australia face significant increase in costs following an anti dumping ruling…

8 June 2026

Capital and carbon: Australian green finance pioneer Martijn Wilder honoured in King’s birthday awards

Martijn Wilder has been recognised for his pioneering work in sustainable finance, renewables, conservation and…

8 June 2026

Anatomy of a renewable finance deal: Developer lands equity for state’s largest solar-battery hybrid

Equity raising and debt funding pitch from listed company provides rare insight into the mechanics…

7 June 2026

“Significant milestone:” Off-grid mine runs 155 consecutive hours on 100 pct renewables and engines off

Off-grid gold mine achieves 155 consecutive hours of running on 100 pct renewables, with "engines…

6 June 2026