Solar farm developer tells Queensland court solar rule change will cost millions

Published by

UPDATE: Queensland solar rule change declared “invalid” by Supreme Court

The developer of the 35MW Brigalow solar farm has told the Queensland Supreme Court that the costs of the project will blow out significantly because of the  government-led changes to installation regulations.

Impact Investment Group, which owns the Brigalow solar farm through Maryborough Solar, says in an affidavit tendered to the court that the new rules introduced by the Queensland Labor government requiring only licensed electricians to mount and fix solar panels would add $2.6 million to its costs.

Impact, with the support of the Clean Energy Council, and the Master Electricians Australia, took the state to court, as we reported last week, and the hearing occurred on Wednesday. RenewEconomy will update the story when a decision is handed down.

According to media reports, the developers of Brigalow put the increased costs of $2,626,000 “as a consequence of the amendment regulation.” That number was confirmed by company sources. Some installers of large rooftop systems say that project costs will blow out significantly because of the rule change.

Lane Crockett – a director of Maryrorough Solar, and head of renewable infrastructure at IIG – said in the reported affidavit that the project’s fixed contract price, and its development timeline, had not factored in the sudden need for around 60 licensed electricians to be employed.

The CEC has also voiced its support for the legal action, while also expressing regret that any such action needed to be taken in the first place.

“The Brigalow Solar Farm feels obliged to challenge the regulation through the courts because the industry has been unable to resolve the matter in discussions with the government since the regulation was announced in April,” said CEC director of energy generation, Anna Freeman.

“In our view, this regulation will increase the costs of projects, reduce employment opportunities for local communities, and lead to a downturn in clean energy investment in Queensland, without delivering any safety benefit.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“A question of trust:” Net zero chief slams state for falling short on targets despite a lot of talk

Net Zero Commission says Australia's biggest state economy is falling well short of targets, despite…

23 July 2026

Regulator suspends 21 companies in crackdown on false statements over solar and battery installs

Regulator says it has suspended 21 companies from the scheme supporting rooftop PV and home…

23 July 2026

Renewable zone to get major boost in mobile and internet coverage as part of benefits package

State government grants to help telcos upgrade mobile and internet black spots as part of…

23 July 2026

Contract awarded for concrete foundations and early works for ten massive spinning machines

Contracts awarded for concrete foundations and other early works for ten huge spinning machines required…

22 July 2026

Rinehart-backed miner achieves 90 pct renewables in June quarter, may take processing plant off grid

Mine backed by net zero opponent Gina Rinehart achieved 90 per cent renewable share in…

22 July 2026

Network seeks partners on upgrade to nation’s largest isolated grid, to cram in more renewables

State-owned utility seeks expressions of interest for project and contract management partners on its massive…

22 July 2026