Big battery joins solar farm to complete “cutting edge” hybrid renewables system

Published by

Singapore-based Vena Energy – which built one of the first large scale solar farms in South Australia and the first big battery in Queensland – has claimed a new Australian milestone: the completion of the largest utility-scale hybrid renewable facility with a single connection to the grid. 

Vena said on Wednesday that it has commissioned a 41.5 MW, one-hour battery energy storage system at its Tailem Bend project, around 90 km south-east of Adelaide in South Australia.

The BESS is the latest milestone of Vena’s Tailem Bend 2 Hybrid Project, which includes an 87 MW solar farm that was commissioned in late 2023. Adjacent to Tailem Bend 2 is the original, 95MW Tailem Bend 1 solar farm, which was one of the first big solar projects to come online in the state in 2019.

Together, the two solar projects deliver a combined capacity of 182 MW, which increases to 223.5 MW with the integration of the battery storage system. 

But it is Tailem 2’s “cutting-edge design” that Vena is most keen to promote. This allows the solar and battery components to operate independently while sharing a single grid connection – “a groundbreaking feature for utility-scale renewable energy projects in Australia,” the company said this week. 

“This hybrid configuration redefines operational flexibility,” said Vena Energy’s head of Australia, Owen Sela.  

“Our system enables simultaneous export of solar power to the grid and independent operation of the battery for energy export or storage.

“By optimising existing grid infrastructure, we are enabling renewable energy to be dispatched when needed, delivering cost-effective power to South Australia.   

“This ability to store surplus energy and meet high-demand periods advances our mission to accelerate the energy transition, while ensuring communities benefit from a smarter, more resilient energy system that supports the state’s 2030 emissions targets and Australia’s net zero future.”

Vena says it has approval for another BESS at Tailem Bend – a much bigger, up to 204 MW / 408 MWh big battery that would store excess renewables from the grid.

“This expansion underscores Vena Energy’s commitment to strengthening energy resilience and advancing South Australia’s 2030 emission reduction goal and Australia’s 2050 net-zero target,” a statement said.

Vena says the project sourced around 50% of its workforce from the local region, including Tailem Bend, Murray Bridge and surrounding areas, with an additional 35% from within the state during peak construction periods. Around 10% of workers identified as First Nations and 14% were female.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

From niche technology to 500,000 households “taking control:” Cheaper Home Batteries hits half-million milestone

The number of Cheaper Home Batteries installations has passed the half-million mark, a huge new…

13 August 2026

Researchers “froth” over new solar recycling method that recovers 99 pct of silver from used panels

A new take on a widely used mining technique called froth flotation can recover "virtually…

13 August 2026

Power plays: Tomago’s big green switch, the Big 3’s lack of ambition, and why Snowy must change its stripes

From the country's biggest energy utilities announcing their profits and outlook, to the country's biggest…

13 August 2026

Edify Energy reaches financial close on another pair of solar and battery hybrid projects

Edify Energy reaches financial close on another pair of solar and battery hybrid projects, in…

13 August 2026

What five Fijian sparkies taught me about remote, off-grid solar and battery systems

When it comes to remote solar and battery storage solutions, the knowledge you leave behind…

13 August 2026

Tomago won’t be 100 pct renewable until 2033, but Squadron and others want to see multiple supply deals

It will take at least six years to make Australia's largest aluminium smelter 100 per…

13 August 2026