Australia’s biggest wind precinct hit by connection delays and cost blowout

Published by

The Queensland government owned CleanCo has pulled its plans to build a big wind farm in what would be the biggest wind energy precinct in the county, citing delays over connection agreements and rising costs for the decision.

CleanCo had proposed to develop its own 103MW wind facility – known as the Karara wind farm – as part of the 1.03GW MacIntyre precinct that is being developed by Spanish energy giant Acciona Energia near Warwick in the south of the state.

“As a result of significant delays to the connection process for the Karara Wind Farm, and subsequent impact to costs, CleanCo is pausing the development of the project,” a CleanCo spokesperson said in a statement.

The major part of the $2 billion project, the 923MW MacIntyre wind farm, is still going ahead. It is majority owned by Acciona Energia and 30 per cent owned by Ark Energy, part of the Korea Zinc group, which will use the output to help power its Sun Metals zinc refinery near Townsville.

Acciona is also planning to add the 1GW Herries Range wind farm to the MacIntyre wind precinct, taking the precinct’s total generation capacity to what is referred to as the “Big Mac” project to more than 2,000MW, making it one of the largest in the southern hemisphere.

The state-owned transmission company Powerlink only recently boasted of erecting the 100th of 167 transmission towers required for the project. It said then it expects the grid construction work to finish by the end of 2023, for a planned commissioning of the first wind power from late 2024.

Image: Powerlink. Powerlink's MacIntyre grid network.
Image: Powerlink. Powerlink’s MacIntyre grid network.

However, RenewEconomy understands that the delays are not related to the timing of the new transmission link, but the actual connection agreement for the Nordex turbines proposed by Acciona at the precinct.

This is not the first time this has happened with a major project in Australia. The Stockyard Hill wind farm in Victoria, still the biggest in the country until MacIntyre is complete, also suffered major delays because of issues around its equipment.

It is understood that CleanCo was not happy to carry the risk of the connection agreement, but Acciona – as a privately owned company – is more comfortable with the situation.

Powerlink confirmed the delays are not on their end. “There are no delays on the Powerlink connection works for the MacIntyre Wind Precinct project,” a spokesperson said.

The decision on Karara represents an increasingly difficult investment environment for new renewable energy projects across the country, despite strong targets by state governments and supportive policies from the federal government.

A lot of the problems centres around the increasing costs of transmission, delays in new links, and connection agreements, and increases in the cost of the wind farms or solar farms themselves.

In the first quarter of this year, for Clean Energy Council says, there were no financial commitments for new wind or solar projects. AGL said last week costs had jumped and wind farm PPAs were being offered at around $70s a megawatt hour, well up from the $40s cited less than two years ago.

Despite pulling out of the Karara wind farm, the CleanCo spokesperson said the money budgeted for the project will still go towards renewable energy development in Queensland.

The state government had provided the equity for CleanCo’s Karara project but it was withdrawn in the latest budget and folded into a revised $500 million package allocated to CleanCo to develop a portfolio of renewable energy projects in Central Queensland.

CleanCo intends to retain its power purchase agreement for around 400MW of wind output from the 923MW MacIntyre wind farm. It expects this PPA to take effect from 2025, when that part of the wind complex is due to be complete.

RenewEconomy has reached out to Acciona and the state government for further comment, and is awaiting a response.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: Governments

Recent Posts

Golden moment: Australia’s biggest wind farm becomes first to reach 1 GW of output

Australia's biggest operating wind farm has set a stunning new record, becoming the first in…

12 June 2026

The quiet battery: What household batteries reveal about flexibility before full orchestration

The passive battery is not a new phenomenon. What is new is that its value…

12 June 2026

State utility eyes 8-12 hour energy storage investment after “standout” success of four-hour big battery

State-owned utility says it is in discussions to invest in non-lithium technologies with up to…

12 June 2026

Depleted batteries and very expensive gas: How a two-day heatwave led to a near doubling of quarterly prices

Batteries have been protecting consumers from price spikes in most states over summer. But they…

12 June 2026

Solar Insiders Podcast: The public power company plugging the gaps

State Electricity Commission CEO Chris Miller on how the government-owned energy company is filling gaps…

12 June 2026

Australia’s electricity market needs better price signals that reflect local conditions

Australia’s electricity prices ignore location, even though the grid doesn’t. This mismatch drives congestion, curtailment,…

12 June 2026