Waterloo Wind Farm extension complete, boosting capacity to 131MW

Published by

An extension of Waterloo Wind Farm near Clare in South Australia has been completed, with the project’s six new 3.3MW wind turbines successfully exporting renewable power to the grid for the first time over the weekend.

OLYMPUS DIGITAL CAMERA

The $43 million project – which has boosted the wind farm’s total capacity by 18 per cent, to 131MW – was funded by Waterloo’s joint owners, Palisade and Northleaf Capital.

Construction, which began in March and employed more than 130 people, was reportedly completed on schedule and on budget by a specialist team led by Palisade Asset Management and power system engineering experts CAT Projects.

Waterloo’s owners agreed to add of the six new Vestas turbines to the existing 37 turbine wind farm after five years of “solid performance” from the Stage 1 development, to boost its production by 18 per cent.

The project was also notable for its appointment of regionally-based company Keppel Prince to manufacture and supply six new turbine towers for the extension.

The job, worth an estimated $3.5 million to Keppel Prince, means all 43 turbines at the South Australian have towers that were manufactured locally.

Waterloo’s owners said on Monday that the first post-expansion export results had been remarkable, with all six new turbines operating well and generation from the entire facility nearing 100 percent capacity late on Sunday afternoon.

The energy generated be the wind farm is sold to EnergyAustralia and Hydro Tasmania via long-term purchase agreements. Additional energy from the Waterloo wind farm extension will be sold independently to customers via the National Electricity Market.

“The project team has done an incredibly professional job to bring this project to a safe and successful close,” Waterloo’s general manager Steve Brown said.

“Expanding an existing wind farm presents a particular set of challenges and we have managed to overcome these and deliver to a demanding schedule, which is testament to everyone who was involved.

“We are really pleased with this outcome – and that our investors’ portfolio now includes additional clean energy generation that will deliver strong earnings over the long term,” he said.

Final tests to ensure full performance reliability of the new turbines are currently in progress.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Huge delivery of wind turbine components arrives in port, ahead of 450 km road journey

Major delivery of wind turbines, blades and other components ahead of 450 km road journey…

27 May 2026

How a wind and battery hybrid could replace a coal plant – and outperform it at almost every level

A "thought experiment" by a China tech giant finds wind-battery hybrids can achieve the same…

27 May 2026

Australia’s first eight-hour battery system moves to full capacity after receiving landmark grid approvals

German energy giant RWE says it received official sign-off to operate Australia's first eight-hour battery…

27 May 2026

SwitchedOn podcast: Inside the world’s largest battery electric ferry

Incat founder Robert Clifford explains how a family-owned Tasmanian company built a ship many thought…

27 May 2026

Gas-based hydrogen hopeful among shortlisted “low-emission” proposals for troubled Whyalla steelworks

A company looking at hydrogen and graphite technologies among two low emission proposals for the…

27 May 2026

We need to reframe the grid discussion from system strength to system behaviour

We are installing inertia for poorly justified reasons, and we are imposing economic penalties that…

27 May 2026