Walkaway wind farm resumes some production after turbine collapse

Published by

The Walkaway wind farm in Western Australia has resumed some production after more than one month off line following the shock collapse of one of its turbines in early June.

One of the wind turbines – number 43 turbine at the 54 turbine wind facility, also known as the Alinta wind farm – fell to the ground around 8.30am local time on June 8. It caused no other damage and no injuries, but it resulted in the facility being switched off while the cause is investigated.

Production at the 89MW facility, owned by Iberdola Australia, resumed on June 12, but only at a very small level, reaching a maximum output of around 6MW since that time.

Source: AEMO.

It is understood that each turbine is being checked for any faults, and a review is also being carried out at other wind farms that are using the same model – a Vestas B82 1.65MW turbine that was installed in 2006.

The Emu Downs wind farm, also in the same region of Western Australia, is another using the same turbine model, but appears to be operating normally. The latest generation of wind turbines being installed by Vestas in Australia are more than three times bigger in terms of capacity.

RenewEconomy understands that a “root cause analysis” is still being worked on, including by an incident management committee led by Iberdrola Australia managing director and CEO Ross Rolfe, but has yet to finalise its report.

Another Iberdrola facility, the Port Augusta Renewable Energy Park in South Australia, which will become the country’s biggest wind and solar hybrid once all the 317MW of wind and solar capacity is installed, has also been offline for most of the past month.

Its operation was suspended on June 23 after severe oscillations caused “flickering” on the local grid, visible to many consumers by the reaction of their lighting.

PAREP was identified as the cause of the problem and production and the commissioning process of the 210MW wind component was halted. The 107MW solar component is not yet complete.

It has yet to resume production as Vestas, which is supplying 50 of its V150-4.2 MW turbines for the 210MW wind component of the project, transmission company ElectraNet and the Australian Energy Market Operator continue their investigations.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: Institutions

Recent Posts

A summer of record renewables, record demand highs and record demand lows, and no blackouts

Australia's main grid boasted a record share of renewables over summer, and experienced record demand…

4 March 2025

Victoria urged to back home batteries and more deep storage, and do it soon

Draft strategy says batteries of all sizes - and deep storage - are critical to…

4 March 2025

New government extends life of 1980s gas plant as shift to renewables limps ahead

NT confirms plans to extend the life of a nearly 40-year old gas plant as…

4 March 2025

Wind turbine collapses on calm day in Oklahoma, another is struck by lightning

A Nordex wind turbine has collapsed at a wind farm in northern Oklahoma with no…

4 March 2025

Pro surfer Josh Kerr makes world-first surfboard from recycled wind turbine blades

First there were shoes, now Australian pro surfer Josh Kerr has made the first surfboards…

4 March 2025

Batteries and grid upgrades deliver better ratings and revenue for blighted wind and solar farms

Remote wind and solar farms and those in what was once known as the "rhombus…

4 March 2025