The Port Augusta Renewable Energy Park, which will be Australia’s biggest wind and solar hybrid facility once complete, has resumed production after a three week hiatus caused by oscillation issues that caused “flickering” in the South Australia grid late last month.

Production was halted at PAREP on June 24 after repeated “flickers” and voltage fluctuations were experienced on the local grid the previous night.

Energy authorities identified the source of the problem as the new Port Augusta Renewable Energy Park, which is owned by Iberdrola Australia and will have a combined capacity of 317MW, making it the biggest of its type in the country.

Production was immediately halted at Parep, which had been working its way through the various stages of commissioning of the wind component of the facility, and had reached an output of around 140MW, out of its total capacity of 210MW.

The 107MW solar component is largely complete but has not yet started its commissioning process. It will operate as a separate generating unit despite being co-located, with its own DUID (market identifier).

Source: NEMLog.

This week, production at PAREP resumed, albeit at very low levels, initially at just a few megawatts, occasionally up to 20MW, and back down again.

RenewEconomy understands that output will continue to be volatile as part of testing to satisfy the transmission operator ElectraNet and the market operator AEMO that the plant’s settings have been fixed.

Once resolved, the wind component will be able to resume at its most recent “hold point” setting of 140MW, before being allowed to move to higher output levels as the commissioning process continues.

Earlier this week, production resumed at the Walkaway wind farm in Western Australia, also owned by Iberdrola, after more than one month offline following the still unexplained collapse of one of the facility’s 54 wind turbines.

 

 

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Peter Hannam joins Renew Economy as senior writer as editorial team expands

Veteran energy and climate reporter Peter Hannam is joining Renew Economy, returning to journalism after…

24 July 2026

Energy Insiders Podcast: Why we make renewable projects so hard

Consultant Shane Quinnell on the many hurdles we force renewable projects to jump over –…

24 July 2026

“Strong endorsement:” Australia’s biggest solar-battery hybrid project locks in finance

Ark Energy becomes the fifth developer in just one week to announce a major investment…

24 July 2026

Australian developer gets funding boost for 2 GW-plus renewable energy plans and big solar battery hub

The developer behind Victoria’s Mortlake Energy Hub has secured around $A245 million from a global…

24 July 2026

Small victory for big wind project navigating tough state planning laws

Plans to build a wind farm near one of country's youngest coal plants win all-important…

24 July 2026

Wake steering: Researchers say turbine realignments could add double digit power gains to wind farms

Researchers says realignment of wind turbines away from the wind can boost output. "Wake steering"…

24 July 2026