Vast Solar and 1414 team up for new attempt at Port Augusta solar storage hub

Published by

Australian concentrated solar company Vast Solar has teamed up with another local thermal storage hopeful 1414 Degrees in the latest attempt to build a large scale solar thermal and storage plan in Port August, South Australia.

The Sydney-based Vast Solar will acquire 50% of the shares in Silicon Aurora, a subsidiary of 1414 Degrees and will jointly operate the Aurora Energy Project, which will feature a combination of  solar thermal, PV, and battery technologies.

The original Aurora project was to have been built by US company SolarReserve, but its $750 million proposal for a 150MW solar tower power plant with eight hours of storage fell by the wayside after it failed tis secure funding, despite being offered $110 million of federal funding set aside in March 2017.

In late 2019, 1414 Degrees bought up the Australian assets of SolarReserve, including the rights to the failed Aurora CSP project, which had secured state approvals for development.

Its own plans to resurrect the project have been evolving over the last few years, with 1414 Degrees weighing up a handful of design plans, including the potential to pilot its silicon-based thermal energy storage technology SiBox.

However, uncertainty around investment has plagued the plans. In the span of only four months, Ovida Infrastructure decided to invest in the project last December, but then in April revised its strategic priorities and pulled out.

Current plans for the project, however, expect to see the development of a 140MW 1- 2- hour battery energy storage system during stage 1, pending a 2023 financial investment decision (FID).

Vast Solar, meanwhile, itself won federal government backing in April this year to build a 20MW CSP project with up to 12 hours of storage near Port Augusta, supported by a renewed promise of $110 million in funding from then federal energy minister Angus Taylor.

Vast intends to use the same modular tower technology that the company says it has successfully demonstrated at Jemalong in NSW, which uses sodium as the heat transfer fluid.

“As per recent comments from the federal energy minister and AEMO, dispatchable renewable energy capacity is what is required to curb the high prices currently being experienced in Australian energy markets,” said Craig Wood, CEO of Vast Solar.

Wood said the companies would be working with the federal government and ARENA to finalise funding for the project, and with state and local governments and other partners to expedite the Aurora project.

“The transaction brings together two highly innovative Australian companies that share a vision for Aurora’s development as a long-term renewable energy project in Port Augusta,” added 1414 Degrees CEO Matt Squire.

“In addition to accelerating the development of our Stage 1 BESS, the Aurora site may also act as a showcase for the establishment of exciting renewable technologies being developed by Vast Solar and 1414 Degrees.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Recent Posts

Remote gold mine sources 88 pct of its power needs in last quarter from wind, solar and battery

One of Australia's biggest gold mines is sourcing nearly 90 per cent of its power…

20 January 2026

SwitchedOn podcast: Why energy companies should be forced to act in their customers’ best interests

Former regulator, Ron Ben-David argues that loyalty penalties, consumer confusion and endless rule-making all stem…

20 January 2026

Gladstone attracts another solar battery hybrid, with $2 billion project that would be Australia’s biggest

A new $2 billion solar and battery hybrid project has entered the federal EPBC queue,…

20 January 2026

New Queensland big battery now fully operational five months ahead of schedule

Akaysha Energy completes its second big battery project - five months ahead of schedule -…

20 January 2026

“When coal breaks down, bills go up:” Anger and frustration as Origin extends life of biggest coal plant, again

Origin confirms Eraring to be kept online until 2029 - nearly four years after its…

20 January 2026

Ireland’s oldest wind farm closes down to make way for one of Europe’s largest projects

Ireland's oldest wind farm decommissioned to make way for expansion of adjoining project that will…

19 January 2026