TransGrid submits plans for Snowy 2.0 transmission link, but route still up in the air

Published by

TransGrid has delivered its preferred plan for the proposed HumeLink transmission network upgrade to energy market regulators, as it takes the first key steps in gaining regulatory approval for the multi-billion dollar investment.

The HumeLink transmission project will lift overall capacity in NSW, alleviate congestion and pave the way for new wind and solar projects, but most of all will be used to connect and distribute power from the huge new Snowy 2.0 pumped hydro project.

TransGrid said it believes Hume could deliver almost $500 million in benefits over the life of the project, which has attracted criticism because of the plan to build a major new link through the Kosciuszko National Park to connect the Snowy 2.0 expansion.

Environment groups have called on TransGrid to change the route or use underground network links in the national park, and local community residents have also raised concerns about the potential impacts on the Tumut airport.

TransGrid has said that it is open to considering potential alternatives, subject to their financial and technical viability, and has committed to improving its engagement with local community members after receiving complaints about its consultation approach.

The Australian Energy Regulator will review the submission and say if it approves the cost of the project, which will then be passed on to consumers. TransGrid anticipates that the project will require an investment of around $2.1 billion.

TransGrid had previously warned that the project’s viability could be at risk after the Australian Energy Market Commission rejected a proposed change to electricity rules that would have allowed the company to ‘front-load’ revenues recoverable by the project. But it appears that TransGrid is now ready to progress.

“In the report, we have demonstrated how the HumeLink project will benefit energy customers and deliver $491 million in net benefits over the assessment period.” acting CEO Brian Salter said.

“TransGrid’s report defines a preferred circuit option for HumeLink that delivers consumer benefit. However, it does not define a route,” Salter added.

“We are committed to consulting in a respectful, timely and effective with landowners and communities as the regulatory process progresses and we thank everyone for their patience as we await the regulator’s response to the report.”

After the project has received investment clearance from the Australian Energy Regulator, it will still be required to seek planning approval from the NSW government, with the project expected to be delivered by late 2026.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by

Recent Posts

One Nation MP sponsors petition to sink sheep farmer-led solar and battery project

Farming family wants to host solar and battery project to underpin and co-exist with farming…

7 July 2026

Regulator bans another company from energy upgrades program because of falsified photos

Regulator bans another company from state's energy upgrades program, because of falsified photos used to…

7 July 2026

SwitchedOn podcast: Electrification won’t blow the grid, if networks can connect with consumers

The Electrify 2515 trial shows that the ability of networks to offer customers real value…

7 July 2026

“It should never have left:” Steel making returns to Newcastle with renewables and no fossil gas

Australia's first new steel mill in three decades will be unlike any that came before…

7 July 2026

“Only so much you can do” with hydrogen and batteries: Jet fuel made from cooking oil to be used at Australian airport

Jet fuel made from used cooking oil will be used at an Australian airport for…

6 July 2026

Planning meeting over solar and battery project cancelled after none of 133 objectors bothers to show up

A public meeting to hear objections to a large solar and battery project in New…

6 July 2026