TransGrid proposes new route options for Snowy 2.0 network upgrades

Published by

New South Wales network company TransGrid has taken steps to assuage concerns about the community and environmental impacts of Snowy 2.0, with the release of new route options for the massive project’s $2.1 billion transmission backbone, known as HumeLink.

HumeLink is a new 500kV transmission line that will connect the federal government-owned Snowy 2.0 project to the main grid in New South Wales and deliver its output to where it might be useful. It will also link Wagga Wagga, Bannaby and Maragle.

As RenewEconomy has reported, new transmission lines are emerging as one of several key new battlefronts in the shift to renewable energy, pitting locals and green groups against major and critical new transmission infrastructure projects whose corridors inevitably take in state and national parklands and/or prime farming regions.

In the case of HumeLink, the project has met with significant opposition both from affected locals and landholders as well as from environmental groups, who have called for TransGrid to consider using underground transmission lines, to limit damage to the Kosciuszko National Park.

In a statement on Friday, TransGrid’s executive manager of major projects, Sean McGoldrick, said the network operator had been examining options to use more public land where it was available and to avoid the airport.

The new options proposed include a new route within Green Hills State Forest which moves proposed transmission onto public land and away from privately owned farmland, as much as possible, and another option for the route east of Batlow to run north of Blowering Reservoir, in a bid to avoid Tumut Airport.

“Engagement with Snowy Valleys Council, the Rural Fire Service and the local community indicated real concern that the transmission line could impact the expansion and operation of Tumut Airport, especially during bushfire season, and so network planners have examined a different option, north of Blowering Reservoir, to the one previously proposed,” McGoldrick said.

“In addition, consultation with landowners and other stakeholders has led to an option utilising more public land in Green Hills State Forest, east of the Yaven Creek community.”

McGoldrick said local landowner consultation would continue on HumeLink and TransGrid would 
“propose new transmission on public land wherever possible, or in parallel to existing infrastructure.

“We will continue to meet with landowners and discuss ways we can consider route options that minimise disruption to them, to their properties and their farm businesses,” he said.

Transgrid has also enlisted the help of former NSW Commissioner for Fair Trading, Rob Stowe, to lead the company’s community engagement on planned transmission infrastructure projects.

A meeting is currently being planned for later this month with landowners in the Kyeamba area, where TransGrid is working to narrow the proposed route corridor in response to “intensive consultation” with landowners.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

The fossil fuel-backed IPA’s deep connections with likely new Liberal premier

The likely new premier of Victoria, and her closest advisors, have deep connections with fossil…

25 November 2026

“Never seen volatility like this:” Solar veteran says industry in crisis due to home battery glut and policy swings

Supply gluts and policy swings causing crisis in home solar and battery market, with deep…

25 November 2026

Chinese energy giant signs up for 400 MW green hydrogen system to make iron and steel in NSW

Builder of world's first zero emissions industrial park brought in help design a 400 MW…

25 November 2026

“One of the few options we have:” Green hydrogen pioneer wins prime minister prize for science

Winner of science prize says green hydrogen is one of the few options Australia has…

25 November 2026

Digital twin to help scale and cut costs of giant Australian renewables to hydrogen projects

Digital twin for proposed renewables-to-hydrogen nodes could cut costs of massive projects by around 20…

25 November 2026

Bluetti Apex 200 Arrives: A versatile 2.5kWh solar generator for RVs, whole-home energy independence

Flagship Apex versatility in a compact 2.5kWh format—big enough for real backup, light enough to…

24 November 2026