Tempo shares still suspended as it seeks deal on solar farm cost blowout

Published by

Listed contracting company Temp Australia has extended the trade suspension in its shares for another two weeks as it continues negotiations over cost blowouts at the Cohuna solar farm in Victoria.

The company had said two weeks ago that it would provide an update to the market on Monday, but instead sought another two week extension, saying only that “negotiations continue to show reasonable progress” but the key terms are not finalised.

Tempo asked for a trading halt, then a suspension of its shares in April, when it also announced the departure of its CEO, CFO and a board member, blaming cost over-runs at a project widely assumed to be the 35MW Cohuna solar farm, where it has a $15 million contract.

Cohuna is the company’s first venture into solar farm construction, but is not the first to run into problems. The multi-billion dollar RCR Tomlinson collapsed last year, primarily due to the impact of budget over-runs, connection delays and cash flow problems at many of the 12 solar farms it had contracted to build.

RCR has now been wound up, and its solar business closed. Ironically, Tempo brought in former RCR chief executive Paul Dalgleish to advise it on the issues it is now facing.

Cohuna, a 34MW (DC)/27MW (AC) project, located 25kms east of Kerang, is a $59 million project that is owned by Italy’s Enel Green Power, which also owns the Bungala solar projects in South Australia. Enel spokespeople did not respond to requests for comment.

Tempo has a $15.1 million contract for the Cohuna solar farm, which last year was one of six solar and wind projects to win the first reverse auction held by the Victoria government as part of its 40 per cent renewable energy target by 2025. It has a 15 year contract with the state government.

The suspension occurred just weeks after the solar farm began construction.

Numerous solar projects have been hit by connection and commissioning delays, and cost over-runs, some of it caused by the need for new equipment to deal with system strength issues.

Some solar plants have been built but not connected. In Queensland, the 65MW Rugby Run solar farm owned by Adani Renewables (pictured above) was “mechanically complete” in late October last year, but for seven months has been sitting idle with no connection and no injection into the grid.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

South Australia orders world’s first 100 pct hydrogen-capable turbines for Whyalla 

South Australia chooses supplier of the world-first hydrogen capable turbines to support its charge towards…

25 November 2024

Indonesia targets 75 GW of renewables as it aims to end fossil fuel generation by 2040

Indonesia, with the fifth biggest fleet of coal power plants in the world, vows to…

25 November 2024

Plibersek defends coal mine approvals amid blockades of Newcastle port

Environment minister Tanya Plibersek defends coal mine approvals as 170 people arrested for blockading world's…

25 November 2024

From finance deal to carbon trade: Here’s what was – and wasn’t – achieved at the COP29 climate talks

Many people are disappointed by COP29. It did not bring transformative change. But it was…

25 November 2024

Rooftop solar and EVs will dominate our grids: How do we reform the energy system around them?

Australia’s electricity system is physically decentralising, but the regulatory response is to extend the current…

25 November 2024

Australia’s bid to host climate COP for first time on hold as fossil lobby ups the ante at fractious Baku talks

Australia's bid to host UN climate talks for first time stalled at fractious Baku COP,…

25 November 2024