Tasmania Marinus Link would work best in fast transition to renewables

Published by

Plans to build a second interconnector linking the wind and hydro-rich island state of Tasmania to the mainland Australian grid could unlock up to $5 billion in new renewables investments, but only if the rest of the NEM keeps up a fast pace of clean energy transition.

A final business case assessment of the proposed $3.5 billion Marinus Link – the key to Tasmania’s goal of being the “battery of the nation” – has found that a installing a second undersea cable across the Bass Strait was feasible at 1500MW capacity and could be in service from as early as 2027.

The newly published $20 million TasNetworks feasibility study – supported by $10 million from the federal government’s ARENA – found that establishing the new link along with supporting transmission would “provide greater benefits than costs under all modelled scenarios.”

On its own, the report said, the Marinus Link was expected to provide an economic boost to regional communities in Tasmania and Victoria in excess of $2.9 billion.

With supporting transmission, it would unlock wider added value up to an estimated $5.7 billion in Tasmania renewables developments, including new wind farms and pumped hydro energy storage enabled by the additional 1500 MW capacity across Bass Strait.

As you can see in the chart above, the benefits improve vastly depending on the pace of the transition to renewable energy – and away from coal-fired power – in other NEM states, and in particular, Victoria.

This, of course, means that any delay to the planned retirement of Victoria’s ageing coal-fired power plants would have a direct negative impact on the business case for the new link.

“If built, Marinus Link could support Australia’s transition to a low emissions future by expanding the renewable electricity generation and storage capacity in Tasmania, which could be exported across Bass Strait to support the National Electricity Market (NEM),” a statement from TasNetworks said on Thursday.

“At present, Tasmania can only export 500 MW as it is limited by the capacity of the existing interconnector Bass Link.”

The business case proposes the best way forward for the new interconnector would be to build it in two separate HVDC cables of 750MW each, on a route running from north west Tasmania near Burnie to the Latrobe Valley in Victoria.

TasNetworks also released the findings of the regulatory investment test (RIT-T) for transmission, which found that the optimal timing for Marinus Link and supporting transmission was for the first 750MW of capacity to come into service in 2028.

Following that, and depending on the scenario used, the timing of the second 750MW of capacity would be installed between 2030 and 2032.

The report acknowledged that while a 2027 target date did not presently optimise benefits under the RIT-T, this timing would still provide net benefits to the NEM over the project’s life under all scenarios modelled, as you can see in the chart above.

TasNetworks said the plan, now, was to begin the design and approvals phase for Project Marinus, for which the Australian government had committed another $56 million through ARENA.

“Tasmania has the potential to support the renewable energy transformation of the NEM that is currently taking place,” said ARENA CEO Darren Miller in comments on Thursday.

“With this business case showing that Marinus Link is feasible, we could see its vast pumped hydro and wind potential playing a key role in providing clean, low cost and dispatchable power to the NEM in the future.”

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024