South Australia’s second big battery goes live, charges up

Published by

South Australia’s second grid-scale energy storage system, the 30 MW/8MWh big battery at the Dalrymple substation on the state’s Yorke Peninsula, is charging up, nine months after installation was completed in April 2018.

ARENA said on Wednesday that the $30 million Energy Storage for Commercial Renewable Integration (ESCRI) project – aka Dalrymple North Battery – had been commissioned and tested and was now live and connected to the National Electricity Market, “making important contributions to energy security and reliability in South Australia.”

The battery, which received $12 million in funding from the federal government’s renewable energy agency, was developed and is owned by transmission provider ElectraNet – owners of the substation – and will be operated by utility AGL Energy under a long-term lease agreement.

As we reported here last month, the battery is a different beast to the Tesla Big Battery, or Hornsdale Power Reserve.

As ElectraNet chief Steve Masters puts it, the ESCRI will be the first battery of its kind in the NEM to provide both regulated network services and competitive market services “to maximise value from its operation.”

On average, Masters says, it can provide backup power to 4500 local Dalrymple customers for 2-3 hours while connection to the grid is being restored.

As Giles Parkinson explained last month, the Darlymple North big battery is primarily designed for fast-frequency control services to help ease constraints on networks, for frequency control, and to “island” the local area and provide power to households and business in case of blackouts elsewhere.

And it is this last function – designed to allow the battery to tap the neighbouring 91MW Wattle Point wind farm, and local rooftop solar – that has apparently caused the delays in the battery’s progress.

Now that it is up and charging, however, ARENA acting CEO Nicola Morris said ESCRI would complement South Australia’s other batteries and reinforce Australia’s role as a leader in large-scale battery technology.

“We’re excited to see that the completion of the ESCRI battery has already helped inform the development of further battery projects around Australia,” she said.

“The ESCRI battery will provide storage to support renewable generation and will provide fast frequency response to stabilise the grid.

“It is clear that grid scale energy storage has a role to play our future energy mix. ESCRI demonstrates that utility scale batteries can deliver a range of market services and back up power when it is needed,” Morris said.

ARENA has funded four grid-scale batteries, including two batteries recently commissioned in Western Victoria and Infigen’s Lake Bonney battery currently under construction in South Australia.

Those interested can watch the progress of the battery on this ElectraNet site. At the time of publication, the ESCRI was at a 79 per cent level of charge, at 9.8MWh.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024