South Australia’s “other” big battery repays ARENA grant after windfall returns

Published by

One of South Australia’s “other” big battery installations, the 30MW/8MWh ESCRI ElectraNet battery storage system at Dalrymple, has earned enough revenue in its first two years of operation to return the $12 million in grant funding provided by ARENA to the project.

In a report published this week as part of a “knowledge sharing” deal that came with the funding, ARENA said the ESRCI had earned $22.6 million in frequency control ancillary services revenue and $319,820 in discharging revenue between December 2018 and December 2020.

“FCAS revenue peaked in the six months from December 2019 to June 2020, earning $15.6 million in addition to $102,000 discharging revenue, from a $76,000 charging cost,” the ARENA report says, indicating it cashed in on the same “islanding” event that deliver a huge windfall to the better known Tesla big battery.

“The arbitrage and FCAS markets provided revenue streams for the battery, allowing ElectraNet to return the $12 million ARENA provided to the project.”

As RenewEconomy reported six months into the battery’s operating life, the South Australia ESCRI – which stands for Energy Storage for Commercial Renewable Integration – is not as big nor as headline grabbing as the Hornsdale Tesla big battery, but it does do a number of things the Tesla battery can’t.

On top of the more standard skills of operating in the FCAS market and trading caps, the ESCRI – which is charged by AGL Energy’s 90MW Wattle Point wind farm – is configured to allow “islanding” of the Yorke Peninsula, to keep local lights on in case of grid problems elsewhere.

The “grid-forming” inverter capabilities it has pioneered on the main grid (the ability to use battery inverters to “create a grid”‘) are considered critically important, as they will be key to fashioning a renewables-based grid without synchronous generation.

The ESCRI has also supplied Fast Frequency Response (FFR) ancillary services into South Australia, reducing constraints on the Heywood interconnector linking SA and Victoria, and delivering increased flows, and reduced the amount of unserved energy to the region following losses of supply.

On this front the battery continues to impress, according to ARENA, which reports that in the two years from December 2018 the ESCRI was called on in 29 system events, responding almost instantly to inject power to arrest dips in voltage or reduce the duration of an outage.

One event in December of 2019 happened when lightning caused a nearby powerline to trip, at which point the battery maintained Dalrymple’s energy supply until the issue was resolved.

Not long after that, a catastrophic failure tripped a series of transmission lines, the report adds. On this occasion, the battery responded immediately, supporting the network to recover from the sudden voltage dip to become stable within 2.5 seconds.

“As one of Australia’s – and the world’s – first large-scale battery storage systems, the project has broken a lot of new ground,” the ARENA report says.

“[It has] delivered the largest autonomous regional microgrid, able to operate both connected to the NEM and also be islanded. In islanded mode, demand for electricity in the region is met entirely by renewables, with network regulation services provided by the battery.

“This has provided insights into what will be required to operate the South Australian electricity system with 100 per cent renewable energy,” ARENA says.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Labor girds for tricky fight for green hydrogen tax credits in last week of parliament

The hydrogen tax credit bill is being introduced to Parliament, with the Coalition opposed and…

25 November 2024

South Australia’s biggest battery charges up as new wave of storage prepares to enter grid

Commissioning has started on what will be the biggest battery in South Australia, with a…

25 November 2024

Bad for consumers: Regulator pings generators and batteries for multiple “rebids” in high priced events

AER says bidding behaviour of some electricity market participants - peaking plants and big batteries…

22 November 2024

Gas lobby hoorays South Australia capacity payment plan as clean energy industry fears backward step

Gas lobby hoorays the proposed South Australia capacity scheme that would include existing gas generators,…

22 November 2024

Australia’s only wind turbine tower maker to close shop, prompts Coalition to ignore its own history

News Australia's only wind turbine tower manufacturer has decided to pack it in has been…

22 November 2024

Energy Insiders Podcast: Changing the rules of the energy game

The rules of Australia's main electricity grid are constantly changing. Should they be completely rewritten?…

22 November 2024